Vietnam.vn - Nền tảng quảng bá Việt Nam

500kV transmission line project 'very commendable and proud'

Báo Thanh niênBáo Thanh niên03/07/2024


In general, the Prime Minister emphasized that the 500kV line 3 project is a national key project, with a large scale, about 519 km long, double circuit, passing through 9 provinces. The project has a very large and massive construction volume, the construction time until completion must last from 3 to 4 years, similar to previously implemented projects.

However, with the direct and drastic direction of the Prime Minister, Deputy Prime Ministers, the Ministry of Industry and Trade , the State Capital Management Committee at Enterprises, the effective participation of the entire political system and local authorities at all levels to socio-political organizations; the consensus and unanimity of the people where the project passes through; the high determination, great efforts, drastic measures, and close adherence to the construction site of the Vietnam Electricity Group (EVN), the National Power Transmission Corporation (EVNNPT)..., the construction time of the projects has been shortened.

Thủ tướng Chính phủ: Dự án đường dây 500kV 'rất đáng khen ngợi và tự hào'- Ảnh 1.

Engineers at the 500kV Pho Noi substation - the final point of the 500kV circuit 3 transmission line project are checking the electrical box at the construction site.

"After nearly 6 months of construction, the project has achieved many positive results, ensuring technical and quality requirements. This is a very commendable and proud result, and also a lesson in leadership, direction, management, and implementation organization to apply to other large projects in localities and the country," the announcement stated.

The Prime Minister highly appreciated the initiative and support of localities, the active participation of the entire local political system; the Ministry of Industry and Trade; EVN, EVNNPT, contractors, construction units and directly engineers and workers at the construction site; staff, engineers and workers of electricity units across the country who came to support the project implementation; thanked the people in the localities who agreed to support the project, gave up their accommodation, farming land and production sites for the project, and actively participated in supporting logistics and transporting materials for the project construction...

Up to now, the project is entering the final stage and needs to urgently complete the remaining work. The Prime Minister requested EVN and EVNNPT to organize a special peak competition, "final", "lightning speed", mobilizing all forces to participate in order to complete the inspection procedures, technical acceptance and organize the inauguration of the project in July, in which it is necessary to do a good job of environmental restoration and sanitation; quickly stabilize the livelihoods of families where the project passes through so as not to affect production, business and the lives of local people.



Source: https://thanhnien.vn/thu-tuong-chinh-phu-du-an-duong-day-500kv-rat-dang-khen-ngoi-va-tu-hao-185240703114448612.htm

Comment (0)

No data
No data
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together
Hanoi is strange before storm Wipha makes landfall
Lost in the wild world at the bird garden in Ninh Binh
Pu Luong terraced fields in the pouring water season are breathtakingly beautiful
Asphalt carpets 'sprint' on North-South highway through Gia Lai
PIECES of HUE - Pieces of Hue

Heritage

Figure

Business

No videos available

News

Political System

Local

Product