The project to renovate and upgrade District Road 195, phase 2, is 4.3 km long, passing through Hong Quang, Doan Ket and Le Hong communes.
This project has no funds for compensation or support for site clearance. 133 households whose areas are included in the project were mobilized to donate land and clear constructions to implement the project. With the unanimous support of the people, the site clearance work for the project has been basically completed. Only a few households are asking the local government to support part of the costs to move constructions on the land.
According to the construction unit, up to now, the project has completed over 85% of the work volume, ensuring the set progress. Currently, the construction teams have completed the items of large box culverts, embankments, cross-culverts, roadbed embankment, and drainage system on a total length of 4 km. Of which, 1.5 km has completed 100% of the work volume. The remaining road section is qualified for pavement. The construction unit strives to put the project into use before August 31.
The project to renovate and upgrade District Road 195 has a total length of 7.8 km, with a total investment of about 95 billion VND. This project is divided into 2 implementation phases. In September 2023, phase 1 of the project with a total length of 4.5 km was completed and put into use. This is a key project of Thanh Mien district in the 2020-2025 term.
DO QUYETSource: https://baohaiduong.vn/khong-kinh-phi-boi-thuong-du-an-duong-huyen-195-o-thanh-mien-van-bao-dam-tien-do-giai-phong-mat-bang-390191.html