Extension of construction work for restoration of the Japanese Covered Bridge relic

Việt NamViệt Nam14/05/2024

img_7168.jpeg
Japanese Covered Bridge restoration project. Photo: IT

After considering the proposal of Hoi An City People's Committee and the Department of Construction on extending the contract for the restoration of the Chua Cau relic, the Provincial People's Committee agreed in principle to extend the contract for this construction project by 180 days to complete the remaining work and volume.
The Provincial People's Committee assigned the People's Committee of Hoi An City (investor) to be responsible for re-checking the legality of the Construction Contract No.
68 dated December 26, 2022 was assigned by the city to the Hoi An Cultural Heritage Management and Conservation Center to sign with the construction contractor. Based on the construction contract signed with the contractor, inspect and determine the causes affecting the contract progress, and impose penalties for violations of contract progress delays if due to subjective reasons of the contractor.

img_7166.jpeg
After the demolition of the Japanese Covered Bridge, Hoi An had to temporarily stop restoring the floor of the relic due to many controversies. Photo: IT

At the same time, organize negotiations and sign a contract appendix with the contractor on adjusting the contract implementation time to ensure that it does not exceed the project implementation time approved by the Provincial People's Committee in Decision No. 834 dated April 5, 2024. It is noted that extending the contract implementation time does not increase construction costs compared to the signed contract.
In addition, calculate and make a detailed plan for the implementation progress of the work contents and remaining volume, and urge and direct the construction contractor to focus on accelerating the implementation progress, completing the project to ensure quality, on schedule, and being extended for acceptance, handover and putting the project into use, and finalizing the completed project according to the provisions of law.
The Provincial People's Committee also requested the departments (including Planning and Investment, Finance, Construction, Culture, Sports and Tourism) and related sectors and units, according to their assigned functions and tasks, to be responsible for monitoring, guiding, inspecting and supervising the People's Committee of Hoi An City in the process of implementing the project to ensure progress, quality and compliance with legal regulations.
Previously, in December 2023, Hoi An City People's Committee decided to temporarily stop the restoration of the floor of the Chua Cau relic (the path across the bridge of Chua Cau) due to many disagreements.

img_7167.jpeg
The construction period of the project was extended by 180 days. Photo: IT

The total cost of the Chua Cau restoration project is 20.2 billion VND, with a construction period of 360 days. The project will start on December 28, 2022.
The Japanese Covered Bridge is a unique architectural work of art, a typical symbol of the World Cultural Heritage of Hoi An. In its history, the Japanese Covered Bridge has gone through 4 centuries and has undergone 7 large and small scale repairs.


Source

Comment (0)

No data
No data
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together
Hanoi is strange before storm Wipha makes landfall
Lost in the wild world at the bird garden in Ninh Binh

Heritage

Figure

Business

No videos available

News

Political System

Local

Product