On March 6, Mr. Ho Huong, Chairman of the Board of Directors of Da Nang Water Supply Joint Stock Company (Dawaco), signed a decision approving the results of the contractor selection for the construction package of the traffic - drainage - lighting items phase 2 under the contractor selection plan of the Cau Do water plant technical infrastructure construction project.
According to the bidding notice, this package costs more than 5.1 billion VND, a lump sum contract. The form of contractor selection is open bidding domestically and online.
The bidding results have 2 participating units: the Joint Venture of Betaco TV&XD Joint Stock Company and Nhat Anh Vinh TV&XL Company Limited and the Joint Venture of Phuc Dang Company Limited and Phuoc Thinh Phat Company Limited.
During the process of evaluating the bidding documents, the expert team determined that when evaluating the experience and capacity of the contractor, the joint venture of Phuc Dang Company Limited and Phuoc Thinh Phat Company Limited, the automatic evaluation results from the national bidding network system on the contractor's financial performance were not satisfactory.
In this case, the joint venture contractor Phuc Dang Company Limited and Phuoc Thinh Phat Company Limited did not meet the requirements on capacity and experience, so they were not considered for further technical and price evaluation.
Inside the Red Bridge water plant.
Only the joint venture contractor Betaco Consulting and Construction Joint Stock Company and Nhat Anh Vinh Consulting and Construction Company Limited met the requirements on capacity and experience and was evaluated as qualified in terms of technique and price.
This consortium won the bid with a Contract Price including VAT of 4.67 billion VND, 8.46% lower than the approved estimated value of the bid package.
Implementation time shall not exceed 150 days from the date of handover of the construction site, excluding force majeure reasons.
Cau Do Water Plant is managed by Dawaco. After 2 phases of construction and upgrading, this water plant has reached 290 thousand m3/day. This is the main water supply for more than 1 million people in Da Nang City, ensuring water supply until 2025.