Vietnam.vn - Nền tảng quảng bá Việt Nam

Speed ​​up construction of 3 key projects

The investor is strongly directing the mobilization of resources, accelerating the construction progress to complete route 991B and Long Son - Cai Mep in 2025, while accelerating the construction of Phuoc An bridge, ensuring on-time completion in 2027.

Báo Bà Rịa - Vũng TàuBáo Bà Rịa - Vũng Tàu18/06/2025

Chairman of the Provincial People's Committee Nguyen Van Tho inspected the progress of Phuoc An bridge.
Chairman of the Provincial People's Committee Nguyen Van Tho inspected the progress of Phuoc An bridge.

The road gradually becomes clear.

After more than 2 years of construction, the Phuoc An Bridge project has reached about 72% of the volume, 3 months ahead of schedule. Main contractors such as 620 Joint Stock Company, 479 Hoa Binh and Trung Nam EC are working in 3 shifts continuously, mobilizing maximum human resources and equipment. Mr. Thai Van Nhat Cuong, Deputy Project Manager of Trung Nam EC Company, said that if the progress is maintained, the project can be completed 4-5 months ahead of schedule and the entire project is expected to be completed in early 2027.

The 991B Road Project, connecting National Highway 51 to the downstream of Cai Mep Port, is in the final stage, striving to open to technical traffic in June 2025. Implementing the direction of the Provincial Party Standing Committee, the Regional Traffic Project Management Board and the provincial agricultural sector have added subcontractors to speed up the progress.

The project's construction has encountered many difficulties due to the terrain characteristics of the sub-tidal zone, slow site clearance in Package 37, fluctuations in material prices, and overlap with existing technical systems such as power lines, gas pipelines, and national highways. However, the investor affirmed that the entire construction force is making maximum efforts to ensure progress and completion in 2025.

The Long Son - Cai Mep road project has a total length of nearly 3.75 km. After completing the work of converting the forest use purpose, the entire route is being deployed simultaneously with the bridge and road sections. To date, the cumulative implementation value has reached about 42.1% of the total construction and installation capital. The road section has reached about 36%, the bridge section has reached 50%. Package 51 has also started construction since the beginning of June 2025.

Mr. Nguyen Van Trinh, Director of the Provincial Regional Traffic and Agricultural Project Management Board, said that the Board regularly inspects and meets with construction units; any delays due to contractor errors will be handled according to the contract. Contractors are required to increase manpower, equipment, and work in "3 shifts" to ensure progress.

2 projects to be completed by 2025

That was the direction of Chairman of the Provincial People's Committee Nguyen Van Tho at the field inspection and working session with construction units and investors of three key traffic projects including Road 991B, Long Son - Cai Mep Road and Phuoc An Bridge on June 8.

The Chairman of the Provincial People's Committee requested to complete Road 991B before August 15, 2025, and directed the Project Management Board to add subcontractors to speed up construction.

For Phuoc An Bridge, the requirement is to complete the approach bridge on the Ba Ria-Vung Tau side (package 38) in 2025; speed up the construction of the extradose main span and the approach bridge on the Dong Nai side, striving to shorten the time from 6-9 months.

For the Long Son - Cai Mep route, Mr. Nguyen Van Tho requested the investor to coordinate with the Department of Finance to complete procedures to extend the Song Rang bridge bidding package, speed up the progress to open to traffic before August 30 and complete the entire route before December 30, 2025.

Along with that, the Chairman of the Provincial People's Committee requested to strengthen field inspections, regular meetings; strictly handle contractors who violate progress, ensure labor safety and environmental sanitation.

Article and photos: TRA NGAN

Source: https://baobariavungtau.com.vn/kinh-te/202506/tang-toc-thi-cong-3-du-an-trong-diem-1045622/


Comment (0)

No data
No data

Same category

Fireworks explode, tourism accelerates, Da Nang scores in summer 2025
Experience night squid fishing and starfish watching in Phu Quoc pearl island
Discover the process of making the most expensive lotus tea in Hanoi
Admire the unique pagoda made from more than 30 tons of ceramic pieces in Ho Chi Minh City

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product