TPO - The Government Inspectorate recommends that the People's Committee of Hung Yen province direct relevant agencies to review legal documents to re-bid to select the investor for the Technical Infrastructure Construction Investment Project of Sub-area A - Urban Area North of National Highway 5 in Pho Noi Urban Area. During the implementation process, if any violations of criminal law are discovered or if by June 30, 2025 the bidding to select the investor has not been carried out, the case will be transferred to the investigation agency...
 |
Through inspections of 19 land use projects in Hung Yen province, the Government Inspectorate (GIA) discovered a series of limitations, shortcomings and violations. Among them is the investment project to build technical infrastructure in subdivision A - urban area north of National Highway 5 in Pho Noi urban area, invested by Hoa Phat Urban Development and Construction Joint Stock Company (Hoa Phat Company). |
 |
The inspection conclusion announcement stated that the technical infrastructure construction investment project of subdivision A of the urban area north of National Highway 5 is one of four projects selected by the People's Committee of Hung Yen province as an investor to implement the housing project without going through bidding to select an investor. |
 |
In addition, the inspection agency pointed out that this project was allocated land since 2018, but by the end of the inspection (May 2023), the land price had not been approved. |
 |
From the above inspection results, the Government Inspectorate recommends that the Prime Minister assign the Provincial People's Committee to withdraw Document No. 1488/UBND-KT1 dated July 14, 2016 on continuing to assign Hoa Phat Urban Development and Construction Joint Stock Company as the investor to implement the project because at this time, the Housing Law 2014 and Decree 99/2015/ND-CP dated October 20, 2015 of the Government do not have regulations on the transition for project implementation by using land funds to create capital for infrastructure construction. |
 |
At the same time, direct competent authorities to review legal documents to re-bid and select investors for projects using land in accordance with the law. |
 |
“During the implementation process, if any violations of criminal law are discovered or by June 30, 2025, the bidding for selecting an investor has not been carried out, the case will be transferred to the investigation agency for handling according to regulations,” the inspection conclusion stated. |
 |
TTCP also recommended that the People's Committee of Hung Yen province direct the Department of Natural Resources and Environment of Hung Yen province to urgently determine the land use fee payable to the budget for the investment project to build technical infrastructure in subdivision A of the urban area project north of National Highway 5 after re-bidding to select the investor according to legal regulations; ensuring correctness, completeness, and no loss. |
 |
It is known that in 2004, Hoa Phat Company was selected by the People's Committee of Hung Yen province as the investor of the urban area project north of National Highway 5, in Pho Noi urban area (My Hao, Hung Yen). |
 |
Next, the People's Committee of Hung Yen province issued Decision No. 358/QD-UB dated February 25, 2005 approving the project with a land use scale of 300 hectares, with a total estimated investment of VND 2,710 billion; By 2010, the detailed construction planning at a scale of 1/500 of subdivision A of the Urban Area project north of National Highway 5 in Pho Noi Urban Area was approved. |
 |
On July 14, 2016, Hung Yen Provincial People's Committee issued Document No. 1488/UBND-KT1 continuing to assign the Company as the investor to implement the project under the land allocation mechanism with land use fee collection. |
 |
Also in 2016, the People's Committee of Hung Yen province issued a decision approving the adjustment of the detailed construction planning at a scale of 1/500 for subdivision A of the urban area project north of National Highway 5 in Pho Noi urban area. |
 |
According to the reporter's records, the project is currently surrounded by corrugated iron, and the project's technical infrastructure is still in disarray. |
 |
Some items inside the project have been completed but abandoned for many years. |
 |
Inside the project land, the investor is planting trees. |
 |
Meanwhile, many project land areas are left fallow for grass to grow. |
 |
At the project site, there is a security guard on duty every day to prevent strangers from entering or leaving the project. |
 |
Sub-area A project of the urban area project north of National Highway 5 is assessed to have a favorable geographical location, located near National Highway 5 connecting Hanoi, Hung Yen, Hai Phong and Quang Ninh... |
 |
The project is also located next to Pho Noi Hung Yen General Hospital. |
Dinh Phong