Phase 1 has dug 16.7/23 million m³, filled 8.26/14.6 million m³; completed 357/447 culverts, 56/62 bridges. The output value reached 4,108 billion VND, equal to 36% of the contract and 62% of the volume of traffic in 2025. The highway is more than 121 km long, starting at Tan Thanh border gate (Lang Son), ending at Chi Thao commune ( Cao Bang ), invested according to TCVN 5729-2012 standards, design speed 80 km/h, according to the plan, it will be traffic by December 19, 2025.
The key project is expected to shorten the distance, open up new development space for the northeastern region, and at the same time strengthen economic , defense and security connectivity in border areas.




Source: https://nhandan.vn/tren-cong-truong-duong-cao-toc-dong-dang-tra-linh-post907762.html