Package XL6 (the section passing through the former Cu Chi, Hoc Mon, and Binh Chanh areas) is approximately 6 km long. A consortium of 5 contractors is deploying hundreds of workers and dozens of machines and equipment, organizing construction in "3 shifts and 4 teams" to ensure the set progress. Currently, package XL6 has reached about 73% completion.

Section 1 of the underpass on Provincial Road 15 has been opened to traffic.



The main construction packages of the Ho Chi Minh City Ring Road 3 project are being directed by the City's Investment and Construction Project Management Board for Transportation Works (Transportation Board), which is focusing on accelerating the progress of contractors.