-After more than 2 years of implementing the project to open a new road from Chi Lang town to the center of Y Tich commune, Chi Lang district, under particularly difficult construction conditions, the road now has a clear shape, satisfying the wishes of hundreds of households inside and outside the project area.
Hard work to open the route
Although the length of the newly opened route is only 7.8 km, the construction conditions for opening the route foundation are very difficult and dangerous.
Mr. Luong Quang Ninh, Deputy Commander of Truong An Lang Son Construction Joint Stock Company (the unit in charge of constructing 2.5 km of the first area of the route) said: Due to the lack of a service road for construction, the units in the consortium of contractors have agreed to develop a detailed construction plan and support each other to the maximum to organize the completion of each work item to ensure safety and quality. The goal is to minimize obstacles and congestion in the work implementation process of each unit.
Accordingly, to ensure construction progress, the units have overcome difficulties, focused on human and material resources with the motto of "taking advantage of favorable weather to continuously construct in 2 shifts", "not afraid of difficulties, not afraid of hardships" to basically complete the project in 2024.
According to the design, to open the route, the contractors had to drill and break rocks, lowering the total of more than 210 thousand cubic meters of rock along the entire route. Mr. Nguyen Manh Hung, Commander of the construction package from Km 5+007 to Km 7+800, Nhan Duc Bac Ninh Company Limited said: The company is responsible for constructing the base on the rocky mountain with a length of 800 meters with a total volume of drilling and blasting, lowering the base according to the design of nearly 40 thousand cubic meters. In the context of difficult construction conditions, the unit has focused highly, mobilized a team of professional engineers and taken advantage of favorable weather conditions for production.
In addition, during the project implementation, all units have performed well in coordinating support and removing obstacles so that the project can be completed as planned. In particular, the role of the investor in performing project management tasks has provided maximum support to contractors and local authorities in site clearance, inspection and supervision of management activities, and use of drilling and explosive materials to ensure security, order, labor safety and project progress.
Mr. Nguyen Anh Tuan, Director of Lang Son Traffic Infrastructure Construction and Maintenance Management Board (project investor) said: During the time assigned as the project investor, the unit has closely followed the provincial agencies and functional units to promptly consult and resolve difficulties and problems arising during the implementation process. Especially the handling of damage to custard apple trees outside the compensation recovery scope due to contractors using explosives to drill and destroy, causing flying rocks to cause damage. Now the project has been basically completed and put into operation, helping to improve traffic activities in the area, contributing to promoting socio -economic development and improving people's lives.
New Road Joy
The project to open a new road from Chi Lang town to the center of Y Tich commune has a total investment of more than 164 billion VND, according to the plan to start construction and complete in the period of 2022 - 2024. According to the detailed construction design approved by the Provincial People's Committee, the length of the new road on the slopes of the rocky mountains is more than 5.5 km and 2.3 km is constructed on a dirt road. This is a project that thousands of households in the rocky mountain communes of Chi Lang district such as: Y Tich, Van Linh, Bang Huu, Bang Mac and Chi Lang town have been looking forward to for many years.
The project has been completed and put into use, making the dream of a road for hundreds of households in Y Tich commune come true. Because opening a new road through the rocky mountains is a very difficult and arduous task. With the support of the people and the determination of the relevant units, the project has helped shorten the distance between the rocky mountain communes connecting with National Highway 1A by over 20 km and travel time has been shortened by up to 40 minutes compared to going by the old road.
Mr. Phung Van Nghia, Deputy Secretary of the District Party Committee, Chairman of the People's Committee of Chi Lang District, said: During the process of implementing the road construction, the people were very supportive, many households were willing to hand over the land first and receive financial support later so that the project could be urgently constructed on schedule. This shows that the people's desire for a new road is very great.
Mr. Luong Van Hoi, a resident of Nam Lan 2 village, Y Tich commune, excitedly said: In 2022, the site clearance work was carried out in the commune. At that time, I was the Party Cell Secretary and Village Chief, and I mobilized the villagers to support the state in handing over the site for construction. The project passed through my family's land, which was more than 4,500 square meters of agricultural land. I handed it over early for the state to build the road. My family was very supportive, because when the road was completed, people from the commune to Chi Lang town only had to travel less than 8 km, while if they followed the old road to National Highway 1A, it was more than 20 km. Having a convenient road helps people develop the economy, giving Y Tich commune in particular and 8 communes in the rocky mountain area of Chi Lang district in general a new look.
Mr. Nong Van Toan, residing in Thach Luong village, Y Tich commune, said: Before there was no road, we carried each load of custard apples on foot along the trails on the rocky mountain slopes to sell, which was very difficult and dangerous. The transportation was laborious, risky and not very effective. Now the road is clear, cars and motorbikes run smoothly, trading is convenient, not as laborious as before, people in Y Tich commune and communes in the rocky mountain area are very happy to have a new road.
In the first days of the new spring of At Ty 2025, we conducted a survey on the new road. In the slightly chilly weather, the peach trees on the rocky mountain slopes were budding, waiting for the spring sunshine to bloom. Along the new road, newly poured concrete steps leading to the custard apple gardens further accentuate the fresh and different beauty of the custard apple area of Chi Lang rocky mountain. This year's Tet, the joy seems to be doubled for the people in this area. With the new road, all the difficulties and hardships of the past have been resolved; the cleared blood vessels will create momentum for this entire rocky mountain area to rise strongly...