On October 30, Chairman of Hanoi People's Committee Tran Sy Thanh signed and issued a Directive on promoting disbursement of public investment capital in the last months of 2024, emphasizing the requirement of "3-shift, 4-shift construction", striving to disburse 95% of public investment capital.
According to the Chairman of Hanoi, in terms of the city's disbursement rate, the results for the first 9 months of 2024 still have many limitations, lower than the national average and the same period in 2023, not meeting the requirements. Many units have not completed the plan as committed, some units even have very low disbursement rates, significantly affecting the overall results of the whole city.
According to Hanoi's plan, the cumulative disbursement of public investment capital committed by units by September 30 is 41,932 billion VND, equivalent to 51.7% of the plan.
However, according to a report on October 25 by the Hanoi Department of Planning and Investment, 33 units have not yet met their commitment to disburse public investment capital, with the total disbursement value that needs to increase to meet the commitment being VND12,738 billion, equivalent to 15.7%. In the remaining months, Hanoi must disburse VND44,927 billion, equivalent to 55.4% of the plan.
Chairman of Hanoi People's Committee Tran Sy Thanh.
In order to strive to complete the disbursement of public investment capital at over 95% according to the plan assigned by the Prime Minister , the Chairman of Hanoi said that the pressure on the workload and the amount of capital to be disbursed in the last months of the year is very large.
Chairman Tran Sy Thanh requested that units with good disbursement continue to maintain, promote and improve implementation efficiency. Units with slow disbursement must urgently review, rectify and immediately overcome existing problems, difficulties and obstacles, take all measures to speed up implementation progress and complete the task of disbursing public investment capital.
Units must speed up the completion of construction investment procedures to soon start construction of projects such as approving contractor selection plans; approving technical designs and estimates; organizing bidding to select construction contractors.
The Chairman of Hanoi assigned the People's Committees of districts, towns and cities to preside over and coordinate with investors, departments and branches to speed up site clearance work, and immediately implement it for areas that meet the conditions, especially projects using the city's budget.
Units need to resolutely direct, manage, and implement measures to speed up the progress of projects such as "construction in 3 shifts and 4 shifts"; "working through holidays, Tet holidays"...
In addition, the head of the Hanoi government requested to strengthen discipline and order, promptly remove difficulties and obstacles, proactively develop and organize appropriate construction solutions, adjust the critical path of project progress to ensure the approved progress, contributing to promoting the disbursement of public investment capital of projects.
Districts, towns and cities are assigned to promote the payment and settlement of public investment capital, not to leave behind the volume of work that has been implemented but not paid for, and to avoid making payments at the end of the year.
The Chairman of the Hanoi People's Committee requested to complete the target of disbursing 100% of the capital plan in 2023, extending to 2024, and strive to disburse the public investment plan in 2024 with the highest results.
In addition, units are also assigned to prepare the best conditions to implement the 2025 public investment plan right from the first months of the year, thoroughly overcoming the situation of "capital waiting for projects".
Source: https://vtcnews.vn/chu-tich-ha-noi-chi-dao-giai-ngan-gan-45-000-ty-von-dau-tu-cong-2-thang-cuoi-nam-ar904841.html
Comment (0)