Focusing all efforts to complete Phung Khoang Lake Park before Lunar New Year

Báo Kinh tế và Đô thịBáo Kinh tế và Đô thị31/12/2024

Kinhtedothi - On the afternoon of December 31, Vice Chairman of Hanoi People's Committee Duong Duc Tuan inspected and urged the implementation of Phung Khoang Lake Park under the Phung Khoang New Urban Area Project (Nam Tu Liem District).


Reporting on the progress of the project, Project Manager Dao Tu Quy said that since December 14, the construction unit has mobilized maximum manpower, equipment, vehicles, and machinery to work day and night. To date, with 39 renovation and repair items, the unit has completed about 60% of the work compared to the original design.

Project manager Dao Tu Quy (blue shirt) reports on project progress. Photo: Lai Tan
Project manager Dao Tu Quy (blue shirt) reports on project progress. Photo: Lai Tan

Mr. Dao Tu Quy added: “The amount of work arising at the project is very large, especially many items after 10 years of construction have now degraded, damaged, need to be renovated, repaired, causing more time than new construction. However, with great effort and determination, after 18 days of construction, the appearance of the park has been changing every day, ensuring a bright and beautiful landscape. Many items such as fences, sidewalks, welcome gates, main gates and side gates of To Huu street; fences surrounding the campus; the square, and internal traffic routes have all been completed.”

After 18 days of construction, the appearance of Phung Khoang Lake Park has been changing day by day. Photo: Lai Tan
After 18 days of construction, the appearance of Phung Khoang Lake Park has been changing day by day. Photo: Lai Tan

Faced with large-scale projects and urgent construction time, the construction unit representative proposed that some projects such as basketball courts, drainage infrastructure connections across Me Tri Street... will be implemented after the Lunar New Year.

Directing at the inspection session, Vice Chairman of the City People's Committee Duong Duc Tuan requested construction units to continue to focus all their efforts on completing all items synchronously.

View of Phung Khoang Lake Park. Photo: Lai Tan
View of Phung Khoang Lake Park. Photo: Lai Tan

Vice Chairman of Hanoi People's Committee Duong Duc Tuan noted that the construction should not involve moving trees, affecting the landscape of the area and the park. In addition, although this is a park in Phung Khoang New Urban Area, it is located on To Huu Street, adjacent to the urban area, so it is necessary to create an open, airy space, without erecting high and hard fences.

The Department of Construction coordinates with the People's Committees of Nam Tu Liem and Thanh Xuan districts to organize management, accompany the construction unit, especially directly direct the adjustment of design documents during the construction completion stage.



Source: https://kinhtedothi.vn/don-toan-luc-hoan-thien-cong-vien-ho-phung-khoang-truoc-tet-nguyen-dan.html

Tag: Park

Comment (0)

No data
No data
68 soldiers who paraded in Russia practice for the music night 'Motherland in the Heart'
The multi-purpose 'iron bird' Yak-130 will stir up the capital's sky on National Day, September 2
Mission A80: 'Stormy' from the rehearsal night to the heroic National Day song September 2nd
Overcoming the sun and rain, practicing for the national festival
Southeast Asian newspapers comment on the resounding victory of the Vietnamese women's team
Wild beauty on Ha Lang grass hill - Cao Bang
Vietnam Air Force practices preparing for A80
Missiles and combat vehicles 'Made in Vietnam' show off their power at A80 joint training session
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product