As a key national energy project invested by Vietnam Electricity Group (EVN), this project will contribute to ensuring national energy security, a vivid demonstration of the spirit of overcoming difficulties and solidarity of the Vietnamese electricity industry.
With a total length of 229.5km, the project is being accelerated to celebrate the 80th anniversary of the August Revolution and National Day September 2.

500kV Lao Cai - Vinh Yen transmission line project.

Despite facing complex terrain and harsh weather, construction units still ensure progress, safety and technical quality.

Lao Cai 500kV transformer station - "Heart" of the project, ready for technical energization on August 19, 2025.

Located on a low hill in Lao Cai, the 17.8ha 500kV transformer station is being completed.

Workers worked 3 shifts continuously, installing equipment and completing infrastructure.



EVN Deputy General Director Vo Quang Lam (third from right) inspects construction work at column 404 in Lap Thach commune, Phu Tho province.

EVN workers pull wires at pole number 404.


Workers performing wire pulling project.





EVN staff coordinated with contractors to closely inspect and supervise construction sites.

The 500kV Lao Cai - Vinh Yen transmission line project is a symbol of the will to overcome difficulties, contributing to ensuring a stable power source for the North and the whole country.
Source: https://baolaocai.vn/du-an-duong-day-500kv-lao-cai-vinh-yen-tang-toc-de-ve-dich-post879714.html