The Eastern bypass project of Dong Ha city (section Km 741+170/QL.1 - Doc Mieu to Km10+187/QL.9 to Cua Viet port) is 13.3km long, passing through Gio Linh commune (including Phong Binh, Gio My, Gio Quang communes and the old Gio Linh town), 13.04km long and Dong Ha ward (passing through the old Dong Giang ward) 0.26km long.
Standing Vice Chairman of the Provincial People's Committee Hoang Nam listened to the report on site clearance work for the Eastern bypass project of Dong Ha City - Photo: ML
Up to now, 11.8/13.29km of land clearance have been handed over to the contractor for implementation. Of which, the section through Dong Ha ward has been completed; Gio Linh commune still has about 1.5km, related to 32 affected cases and 30 tombs. Of which, there are currently 4 households that do not accept the relocation and support plan. In addition, the resettlement area in Phong Binh commune and the old Gio My commune, which has been under construction since the end of May 2025, has not been completed yet; the technical infrastructure (electricity, water, telecommunications) has not been completely relocated.
The section from Nguyen Hoang intersection to the south of Song Hieu bridge has a total investment of 230 billion VND, with implementation progress from 2023 - 2025. The project is 4.26km long, passing through Nam Dong Ha ward (including Dong Le and old Dong Luong wards), with a total recovered area of about 16.93 hectares and 259 affected subjects. To date, the project's site clearance work has been basically completed.
The Eastern bypass project of Dong Ha city, from Nguyen Hoang intersection to Song Hieu bridge, has basically completed site clearance work - Photo: ML
At the field inspection, Standing Vice Chairman of the Provincial People's Committee Hoang Nam acknowledged the efforts of relevant units in the implementation process, removing difficulties to speed up the project progress. He requested localities to promptly acknowledge, commend and reward households that have made positive contributions, creating favorable conditions for site clearance work. At the same time, research construction plans to ensure progress and quality of the project, comply with technical regulations on foundations, anti-subsidence...
For the remaining sections of the route, the Standing Vice Chairman of the Provincial People's Committee requested relevant localities to strengthen mass mobilization work, meet and dialogue with people; coordinate with contractors to come up with reasonable solutions in accordance with regulations. Consistent with the viewpoint of creating maximum conditions for the people, so that people in affected areas are not disadvantaged when the project is implemented, however, all options must be reasonable, in accordance with regulations and ensure that there is no precedent, no difference in support level compared to households that have accepted the previous support options. Contents beyond the authority must be promptly reported to the Provincial People's Committee for consideration and handling in accordance with regulations, including enforcement options. By the end of July 2025, site clearance on the entire route must be completed.
The Standing Vice Chairman of the Provincial People's Committee also emphasized a number of solutions to speed up the project implementation progress, noting the clear assignment of people, responsibilities for each individual, group and specific timeline.
Mai Linh - Hoang Hung