This is the target set by the National Power Transmission Corporation for the Gia Loc 220kV Transformer Station and Transmission Line Project (Hai Duong).

Báo Hải DươngBáo Hải Dương21/03/2025

tram-220kv-gia-loc-2-.jpg
At Gia Loc 220kV transformer station, the construction unit has completed many parts of the work such as transformer foundation, column foundation, busbar wire hanging, self-contained transformer station... (photo provided by the facility)

Accordingly, this unit strives to complete the Gia Loc 220kV transformer station project before June 30.

By March 21, the construction unit had completed work such as the road to the transformer station, transformer foundation, equipment pillar foundation, drainage system, emergency oil tank, installation of busbar gate poles, pulling and hanging busbar wires, self-contained transformer station...

For the 220kV line, all 19 poles have been erected, 5/14 anchorages have been pulled, and 3 anchorages are under construction.

The Gia Loc 220kV Transformer Station Project is invested by the National Power Transmission Corporation and built in Gia Phuc Commune (Gia Loc). The 220kV connection line passes through Gia Phuc and Gia Xuyen Communes (Hai Duong City). The project has a scale of 3 220kV transformers, with a total capacity of 750 MVA. In this phase, 2 transformers will be installed, each with a capacity of 250 MVA.

The 220kV line consists of 4 circuits from the 220kV Gia Loc transformer station, connecting to 2 circuits of the 220kV Hai Duong - Pho Noi line, with a route length of about 5.37 km.

tram-220kv-gia-loc1(1).jpg
For the power line section, the construction unit has completed all 19 column foundation positions and is pulling the wires for the anchorages (photo provided by the facility).

The completion of the Gia Loc 220 kV Transformer Station project will significantly contribute to ensuring electricity supply for Hai Duong province and neighboring provinces from this year's hot season. This is an area with rapid economic growth, with a huge demand for electricity for production and daily life.

THANH HOA

Source: https://baohaiduong.vn/phan-dau-dong-dien-tram-bien-ap-220kv-gia-loc-truoc-30-6-407761.html


Comment (0)

No data
No data

Same tag

Same category

Re-enactment of the Ly Dynasty's Mid-Autumn Festival at Thang Long Imperial Citadel
Western tourists enjoy buying Mid-Autumn Festival toys on Hang Ma Street to give to their children and grandchildren.
Hang Ma Street is brilliant with Mid-Autumn colors, young people are excitedly checking in non-stop
Historical message: Vinh Nghiem Pagoda woodblocks - documentary heritage of humanity

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;