Vice Chairman of the City People's Committee Hoang Hai Minh inspected the Phong Dien - Dien Loc rescue route.

On the afternoon of May 12, Vice Chairman of the Hue City People's Committee Hoang Hai Minh inspected the progress of site clearance and construction of traffic projects in Hue City, including the Phong Dien - Dien Loc rescue route; the coastal road combined with the Thuan An seaport overpass and a number of traffic routes in Hue City.

The Phong Dien – Dien Loc rescue route is over 16.2km long; the starting point intersects with National Highway 1A in Phong Thu Ward (Phong Dien Town) and the end point is at Dien Loc beach area (Phong Phu Ward – Phong Dien Town). The project (DA) has a total investment of over 770 billion VND, approved in 2010, invested by the Hue City Traffic Construction Investment Project Management Board.

Currently, the project is being actively implemented. Notably, the section from Km1+500 to Km9+800, along with Thiem Bridge and Bau Bang Bridge, has been completed and put into operation. The section from Km9+800 to Km14+500 and the intersection with National Highway 49B has basically completed the foundation and cement concrete road surface with a width of 15m. For the railway overpass - one of the important works of the project, the right unit has been completed. The bridge is 66.3m long, consisting of two units, each unit is 15.5m wide (total 31m). The remaining unit is under construction of the bridge deck.

Through field inspection, Vice Chairman of the City People's Committee Hoang Hai Minh requested the investor and construction units to focus on speeding up the progress, mobilizing maximum resources, machinery, equipment and workers to complete the remaining items as soon as possible, striving to ensure the route is opened in 2025 as planned.

For completed and put into operation sections, investors and contractors need to be responsible for ensuring smooth traffic, avoiding waste and affecting the legitimate travel needs of people. Vice Chairman of the City People's Committee Hoang Hai Minh also requested that the Hue City Traffic Construction Investment Project Management Board strengthen on-site inspection and supervision, promptly urge contractors to closely follow the progress, ensure quality and labor safety during project implementation.

Vice Chairman of the City People's Committee Hoang Hai Minh inspected the site clearance work at the coastal road project combined with the Thuan An seaport overpass.

The coastal road project combined with the Thuan An seaport overpass is one of the key, large-scale traffic projects, which started construction in March 2022 with a total investment of about VND 2,400 billion in phase 1. The Thuan An seaport overpass is about 2.36 km long, the longest seaport overpass in the Central region. To date, the project has been closed and is expected to be technically opened to traffic on September 2.

Inspecting the site clearance work at this project, Vice Chairman of the City People's Committee Hoang Hai Minh highly appreciated the efforts of relevant units in site clearance work, and at the same time requested to continue to ensure this progress during the implementation process.

Vice Chairman of the City People's Committee Hoang Hai Minh said that the coastal road project combined with the Thuan An seaport overpass is an important project in the city's transport infrastructure development strategy, contributing to connecting dynamic regions, creating favorable conditions for socio-economic development, especially in coastal areas, remote areas. The Vice Chairman of the City People's Committee emphasized that the units continue to promote advocacy and dialogue so that people understand the common interests, thereby promptly handing over the site, creating favorable conditions, ensuring construction on schedule.

Le Tho