Vice Chairman of the Provincial People's Committee Ngo Hanh Phuc requested to completely resolve the problems of the 500kV Lao Cai - Vinh Yen Project.

On July 16, 2025, the working delegation of the Provincial People's Committee led by Comrade Ngo Hanh Phuc, Member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee, inspected the field and had a working session with the communes of Khanh Hoa, Muong Lai, Luc Yen, Lam Thuong, Tan Linh to urge and remove difficulties and obstacles related to the Lao Cai - Vinh Yen 500kV Project.

Báo Lào CaiBáo Lào Cai16/07/2025

Also attending were leaders of the Department of Industry and Trade, Department of Agriculture and Environment, representatives of Power Project Management Board 1 and related parties.

The 500kV Lao Cai - Vinh Yen project is a national key project, playing a particularly important role in releasing the capacity of hydropower plants in the Northwest region and ensuring energy security for the northern provinces. With urgent requirements, the Prime Minister has directed that the project must be completed and energized before August 19, 2025 to celebrate the country's major holidays.

z6811171513257-7d352adfe5ceb49677b2791c5aecf378-6334.jpg
Working scene.

According to the report of the Power Project Management Board 1, as of July 15, 2025, the entire line has completed 95.30% of the pier foundation construction (446/468 locations), and the steel pole erection has reached 39.53% (185/468 locations). However, the wire pulling work has only reached 0.83% (2/242 anchorage spaces).

In 5 communes of Khanh Hoa , Tan Linh, Lam Thuong, Luc Yen and Muong Lai, the foundation construction work has been completed at 75/82 locations and 20/82 steel columns have been installed.

Regarding site clearance, 100% of the foundation and column sites have been handed over. However, compensation, support and resettlement within the corridor are still facing many difficulties, with the overall plan not yet approved, especially issues related to residential land and resettlement arrangements for households.

z6811171511689-e10b16bc56a217708b05d2cf6d8df84b-4188.jpg
Leaders of the Department of Agriculture and Environment spoke at the meeting.

Working with leaders of 5 communes: Khanh Hoa, Muong Lai, Luc Yen, Lam Thuong, Tan Linh, representatives of the Power Project Management Board 1 and contractors at the headquarters of the People's Committee of Luc Yen commune; after listening to the localities, investors and related parties reporting in detail on specific difficulties and problems, Vice Chairman of the Provincial People's Committee Ngo Hanh Phuc emphasized: There is not much time left, all levels, sectors and localities must act decisively and with the highest responsibility.

He requested that localities immediately review and specifically identify the remaining households that have not been resolved.

It is necessary to focus on resolving outstanding cases, especially households that cannot arrange resettlement themselves, in order to have timely support plans.

Regarding the resettlement plan, he requested that for households that can take care of their own resettlement, the government should support them with policies and procedures; for households that cannot take care of their own resettlement, it is necessary to clearly identify the location and arrange suitable resettlement. This work requires close coordination with investors and related units for implementation.

z6811171465311-76b06b2e9080a299e237edb99f66dc2f.jpg
z6811171481234-851f70efc6f5bd81b13d61e36835287f.jpg
z6811171477590-8b72ed600719c99aa5c2c72d97ee7787-3407.jpg
Commune leaders reported at the meeting.

Regarding the progress and implementation plan, the Vice Chairman of the Provincial People's Committee set a specific timeline to complete compensation, support and resettlement work to hand over the site to the investor before July 20, 2025. Require relevant units to closely coordinate, promptly handle arising problems; strengthen propaganda and mobilize people to ensure consensus and cooperation.

He also requested the investor to strengthen supervision and coordination with construction units. Local authorities need to support and closely coordinate with investors and people; there must be synchronous coordination between forces such as the police, army, and departments to ensure security, order and support people during the construction process.

Earlier, in the morning of the same day, Comrade Ngo Hanh Phuc and the working group went directly to the field in Khanh Hoa, Muong Lai and Luc Yen communes to inspect locations facing difficulties in site clearance, areas planned for resettlement and the actual construction progress of the contractor. At the inspection points, the Vice Chairman of the Provincial People's Committee listened to the opinions and concerns of the people and the difficulties of the local authorities and the construction unit.

Source: https://baolaocai.vn/pho-chu-cich-ubnd-tinh-ngo-hanh-phuc-yeu-cau-giai-quyet-dut-diem-cac-vuong-mac-cua-du-an-500kv-lao-cai-vinh-yen-post648928.html


Comment (0)

No data
No data
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?
Taste of the river region

Heritage

Figure

Business

No videos available

News

Political System

Local

Product