Phuoc Son requests extension of contract for construction of road connecting Phuoc Nang commune

Việt NamViệt Nam10/09/2024


ps-6982.jpg
Many road projects in Phuoc Son are behind schedule due to specific difficulties. Photo: D.N

According to the People's Committee of Phuoc Son district, in 2021, the Provincial People's Committee signed Decision No. 2079 approving the plan to select a contractor for the traffic road project connecting Phuoc Nang - Phuoc Chanh communes; implementation time
Construction contract is 900 days.

However, in recent times, the weather in Phuoc Son district has been complicated, with the dry season being "sunny in the morning and rainy in the afternoon", and the rainy season lasting continuously for many months. In particular, in 2022 and early 2023, the weather was unusual and there was a lot of rain, making the construction of roadbed, bridge, and culvert excavation projects very difficult, and the transportation of machinery, equipment, and materials to the construction site was often interrupted...

In addition, compensation, site clearance and handover of construction site to the contractor encountered many difficulties. In the route corridor, there are a number of large trees that must go through property recovery procedures. The contractor has no basis to cut them down and must wait for the opinions of the authorities, which affects the construction of the roadbed.

da-phuoc-son-1670.jpg
Phuoc Son District People's Committee requests to extend the construction contract implementation period until November 30, 2024. Photo: D.N

In order to have a basis to extend the construction contract performance period and continue to implement the project, Phuoc Son District People's Committee proposed that the Provincial People's Committee and the Department of Transport consider allowing an extension of the construction contract performance period until November 30, 2024.

Regarding the above issue, the Provincial People's Committee requests the Department of Construction to preside over and coordinate with relevant departments, branches and units based on the proposal of the Phuoc Son District People's Committee to inspect and guide the settlement according to its authority; in case of exceeding its authority, it shall advise the Provincial People's Committee to consider and settle in accordance with current regulations of law.



Source: https://baoquangnam.vn/phuoc-son-xin-gia-han-thoi-gian-thuc-hien-hop-dong-thi-cong-duong-noi-xa-phuoc-nang-phuoc-chanh-3140833.html

Comment (0)

No data
No data
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?

Heritage

Figure

Business

No videos available

News

Political System

Local

Product