Construction of Provincial Road 830E is still facing land clearance issues.

The Provincial Road (DT) 830E project (the section from the Ho Chi Minh City - Trung Luong Expressway interchange to DT830) is one of Tay Ninh province's key transportation projects, playing a significant role in connecting major arterial routes, reducing traffic congestion, and creating momentum for socio-economic development. Currently, the province is urgently directing relevant units to focus on resolving difficulties, accelerating construction, and clearing the land.

Báo Long AnBáo Long An01/12/2025

An Thanh Bridge is part of the Provincial Road 830E project.

The investment project for the construction of the DT830E road section was approved by Decision No. 8744/QD-UBND, dated September 19, 2022, with a total investment of over 1,213 billion VND, to be implemented from 2022-2025. The DT830E project commenced in April 2023, spanning over 9.3km, starting at the Ben Luc interchange of the Ho Chi Minh City - Trung Luong expressway (Ben Luc commune), and ending at the connection point with DT830 (Long Cang commune).

Phase 1 involves investing in two parallel roads along the route, each consisting of two 7m wide mixed-traffic lanes, one 2.5m wide lane for non-motorized vehicles, and the construction of river crossings on both parallel roads. The connecting road to DT830 will be a complete 6-lane road, 20m wide, with a 30m roadbed. The completed phase will include an 8-lane expressway, two emergency stopping lanes, and a 4-lane mixed-traffic parallel road (2 lanes in each direction).

According to Nguyen Van Hung, Director of the Long An Investment and Construction Project Management Board, as of November 20, 2025, the section from the DT830 intersection to Nguyen Van Nham road is being implemented by two consortiums of contractors. On the left side of the route, the Nui Hong - Tan Nam - 622 consortium has completed the concrete surface of the An Thanh bridge, constructed the embankment with red sand and gravel, and ensured traffic safety, with a completion value of 56.24%. On the right side of the route, the Cau 14 - DV&TM 68 - Thang Loi consortium has achieved 49.5% completion.

The section from Nguyen Van Nham Street to National Highway 1 is also under simultaneous construction. On the left side of the route, the IDICO - An Hoa Joint Venture is constructing cement-soil piles, reinforcing sand embankment, sand filling, red gravel and crushed stone aggregate filling, and drainage system, with the value of work completed reaching 38.36%. On the right side of the route, the LH E&C and BMT Joint Venture is constructing cement-soil piles, reinforcing sand embankment, sand filling, red gravel aggregate filling, precast components, drainage system, and traffic safety measures, with the value of work completed reaching 48.38%.

Land clearance for the project, with a total investment of over 2,494 billion VND, is being implemented from 2021 to 2025. To date, the Provincial Land Fund Development Center (Ben Luc Branch) has paid compensation to 822 out of 878 cases, totaling 1,488.46/1,636.96 billion VND, with 38.53/40.16 hectares handed over. However, 56 households (covering 1.63 hectares) have not yet received compensation, totaling 154.5 billion VND, due to disagreements over compensation rates, requests for full compensation for land and houses, or requests for resettlement.

“As of November 20th, the total length of land yet to be handed over is approximately 950m/4,500m, mainly concentrated in 7 locations: the intersection of DT830 (An Thanh commune); the location of pillars T7-T8 and the access road to abutment M2; the intersection of Phuoc Tu road; the intersection of DT830C; the section from Km4+580 to Km4+800; the section from Km4+760 to Km5+160; ​​and the intersection with National Highway 1,” Mr. Nguyen Van Hung informed.

The delay in land clearance has resulted in a lack of coordinated implementation. Furthermore, recently, some contract packages have been affected by prolonged rainy and stormy weather and a shortage of stone materials.

Currently, the province is making efforts to resolve obstacles and accelerate the progress of the DT830E project. Based on this, the Long An Investment and Construction Project Management Board is actively urging contractors to adhere to the contract schedule; coordinating with the People's Committees of My Yen and Ben Luc communes to encourage households that have received compensation to hand over the land early. The Provincial Land Fund Development Center is tasked with urgently completing the infrastructure of the resettlement area to accommodate eligible households.

Le Duc

Source: https://baolongan.vn/thi-cong-duong-tinh-830e-con-vuong-giai-phong-mat-bang-a207527.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Same author

Heritage

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
Dong Nai City undergoes transformation.

Dong Nai City undergoes transformation.

Vietnamese Tet holiday travel

Vietnamese Tet holiday travel

Sweet Kiss

Sweet Kiss