The Ring Road 4 Project of the Capital Region, belonging to the group of important national projects, passes through 3 provinces and cities ( Hanoi , Hung Yen and Bac Ninh), connecting the Hanoi - Lao Cai and Noi Bai - Ha Long expressways, with a length of 112.8km with a total investment of phase 1 of about 85.8 trillion VND. The project started construction in June 2023.
Of which, the section passing through Bac Ninh province has a route length of 35.3km, including: 25.6km of Ring Road 4 and 9.7km of the route connecting Ring Road 4 with Noi Bai - Ha Long Expressway. The total investment is 5,274 billion VND.
The Prime Minister, Minister of Transport Nguyen Van Thang, and Secretary of the Bac Ninh Provincial Party Committee Nguyen Anh Tuan presented gifts to encourage engineers and workers at the construction site. (Photo: VGP/Nhat Bac)
According to the Resolution of the National Assembly, Bac Ninh is assigned to implement 2 component projects: The component project of compensation, support, and resettlement in Bac Ninh province and the component project of construction of parallel roads in Bac Ninh province.
Regarding site clearance, the province has now handed over 364/374 hectares, accounting for 97.2% of the total site area to the investor, and the remaining 2.8% of the residential land area is expected to be handed over by the end of November 2024. Local leaders are resolutely directing the completion of 11 resettlement projects.
Prime Minister Pham Minh Chinh listens to a progress report on the implementation of the investment project to build the Ring Road 4 of the Hanoi Capital Region through Bac Ninh province. (Photo: VGP/Nhat Bac)
The project is divided into 3 packages and organized into 24 construction teams. Bac Ninh province has strengthened its direction to remove difficulties and obstacles, requiring contractors to work in 3 shifts and 4 teams to speed up the project implementation progress.
Strive from September to November 2024 to increase the total construction output to more than 400 billion VND, basically complete the project in 2025 (for sections that have been handed over in 2023) and the remaining items in 2026, striving to complete the entire project in April 2026, 7 months ahead of schedule.
The biggest difficulty at present is the supply of sand and earth for filling because Bac Ninh does not have any material mines. Regarding this issue, the province has established an interdisciplinary working group to contact neighboring provinces such as Bac Giang, Lang Son, and Phu Tho to access supply sources.
Checking the progress and encouraging engineers and workers at the construction site in Thuan Thanh town, Prime Minister Pham Minh Chinh directed Bac Ninh province to focus on completing the site clearance so that construction can begin as soon as it is available.
Actively relocate technical works such as power transmission poles; work and coordinate with other localities to ensure supply of raw materials.
The Prime Minister encouraged engineers and workers at the construction site in Thuan Thanh town. (Photo: VGP/Nhat Bac)
The Prime Minister asked contractors to mobilize machinery and human resources to work in 3 shifts, "eat and sleep quickly", and work through Tet and holidays.
During the construction process, the consulting and supervising force must strengthen inspection and supervision to ensure quality and progress, and promptly carry out payment and settlement work.
The Prime Minister also requested to further shorten the progress, by December 31, 2025, the project section through Bac Ninh province must be completed.
"The project's early completion will open up new development space, and the people and businesses of Bac Ninh will enjoy it. Therefore, leadership and direction must be clear about people, work, responsibilities, implementation time, effectiveness, and products," the Prime Minister directed.
Also at the construction site, the Prime Minister gave his opinion on how to resolve difficulties related to the investment in three bridges on Ring Road 4, including Me So Bridge (Hung Yen Province), Hong Ha Bridge (Hanoi) across the Red River and Hoai Thuong Bridge (Bac Ninh Province) across the Duong River.
The Prime Minister requested the Ministry of Planning and Investment to coordinate with the Ministry of Transport and three localities to urgently report to competent authorities for consideration and decision to ensure the progress of the entire route.
Source: https://www.baogiaothong.vn/thu-tuong-yeu-cau-rut-ngan-tien-do-vanh-dai-4-qua-bac-ninh-192240922114137165.htm