Overall progress of Rach Mieu 2 Bridge Construction Investment Project to date has reached 82.54%. |
Accordingly, the road section under construction on the entire 14km route (100% completed), the units are currently unloading, the progress is 80%, the asphalt concrete is 22%. It is expected that the entire route on the Ben Tre side will be completed before June 30.
Rach Mieu 2 main bridge has installed the 104th/112th cable-stayed bundle. |
Regarding the bridges, up to now, 4/6 bridges have been completed (Xoai Hot bridge, My Tho bridge, Tam Son bridge and Ba Lai bridge), the remaining 2 bridges are under construction (Rach Mieu 2 main bridge and Song Ma bridge).
It is expected that by June 30, all 5/5 bridges on the route will be completed and the approach roads will be basically completed.
The main bridge section - Rach Mieu 2 bridge is 15% ahead of schedule (100% completion of tower pier P19 & P20) |
The main bridge section - Rach Mieu 2 bridge is 15% ahead of schedule (100% completion of tower pier P19 & P20); 12/14 main bridge deck blocks completed and girder block 13 under construction; 104/112 stay cable bundles installed).
The main bridge section - Rach Mieu 2 bridge is 15% ahead of schedule. |
Mr. Tran Van Thi emphasized: “In order to demonstrate determination and aim to complete the entire Rach Mieu 2 Bridge Project by September 2, My Thuan Project Management Board and other units are seriously implementing construction in 3 shifts and 4 teams (with 30 construction teams; about 150 construction equipment; 500 workers and 83 technical staff). All are determined to speed up the progress further, aiming to close the main bridge of Rach Mieu Bridge on April 30”.
Construction units day and night |
According to sggp.org.vn