Ho Chi Minh City: Vice Chairman Bui Xuan Cuong inspects traffic works, clears traffic jams

On the afternoon of July 31, Vice Chairman of Ho Chi Minh City People's Committee Bui Xuan Cuong went to the field to inspect the progress of key traffic projects and directed to have optimal solutions to solve traffic congestion at Tan Van intersection.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng01/08/2025

At Tan Van intersection (Dong Hoa ward, Ho Chi Minh City) of the Ring Road 3 project - Ho Chi Minh City, the Traffic Construction Investment Project Management Board (Traffic Board) reported on the progress and difficulties in the project construction process.

Relieve traffic congestion

In particular, after hearing the report on traffic jams on National Highway 1A, Dong Nai Bridge and National Highway 51 ( Dong Nai ), Vice Chairman of Ho Chi Minh City People's Committee Bui Xuan Cuong requested the Traffic Department to continue monitoring and coordinating with Ho Chi Minh City Police to survey and re-evaluate to choose the most optimal solution to solve traffic jams in this area during the construction of Tan Van intersection.

TP.HCM: Phó chủ tịch Bùi Xuân Cường kiểm tra công trình giao thông, tháo gỡ ùn tắc- Ảnh 1.
Tan Van intersection is under construction.
PHOTO: DO TRUONG

Vice Chairman Bui Xuan Cuong also requested the Traffic Department to coordinate with press agencies to promptly inform people about traffic flow and guidance through the Tan Van intersection area during construction.

TP.HCM: Phó chủ tịch Bùi Xuân Cường kiểm tra công trình giao thông, tháo gỡ ùn tắc- Ảnh 2.
Vice Chairman Bui Xuan Cuong (2nd from right) inspects traffic works at Tan Van intersection
PHOTO: DO TRUONG

According to Binh Duong Traffic Department (still using the old name after the merger), the traffic congestion in this area has been basically resolved. However, if the road connecting My Phuoc - Tan Van road with National Highway 1A, which is only about 100m long, is cleared and opened soon, along with the putting into use of the road connecting DT 743B road with the new Eastern Bus Station, the local traffic congestion will be resolved and traffic pressure on the area will be relieved.

TP.HCM: Phó chủ tịch Bùi Xuân Cường kiểm tra công trình giao thông, tháo gỡ ùn tắc- Ảnh 3.
Nearly 100m stretch of road has not been cleared yet, Vice Chairman Bui Xuan Cuong requested quick clearance to resolve traffic jams
PHOTO: DO TRUONG

Inspecting the nearly 100m stretch of road that has not been cleared, Vice Chairman Bui Xuan Cuong requested relevant agencies and units to coordinate with Dong Hoa ward (HCMC) to clear the remaining 8/12 households to construct and clear this connecting road.

Inspecting the construction progress of Binh Chuan intersection, including the intersection with National Highway 13, Ring Road 3 - Ho Chi Minh City and the project to upgrade and expand National Highway 13, Vice Chairman Bui Xuan Cuong acknowledged and highly appreciated the clearance, handover of land and construction progress of the project.

TP.HCM: Phó chủ tịch Bùi Xuân Cường kiểm tra công trình giao thông, tháo gỡ ùn tắc- Ảnh 4.
Construction of Binh Chuan intersection, Ring Road 3 - Ho Chi Minh City

Regarding the project to upgrade and expand National Highway 13, Vice Chairman Bui Xuan Cuong requested the investor, Becamex IDC Corporation, to urgently construct the sections that have been handed over and relocate the technical infrastructure.

TP.HCM: Phó chủ tịch Bùi Xuân Cường kiểm tra công trình giao thông, tháo gỡ ùn tắc- Ảnh 5.
National Highway 13 intersection with Ring Road 3 - Ho Chi Minh City is under construction.
PHOTO: DO TRUONG

Vice Chairman Bui Xuan Cuong also proposed to consider re-planning Binh Duong Bus Station on 30/4 Street (Thu Dau Mot Ward, Ho Chi Minh City) because when Ring Road 3 - Ho Chi Minh City is opened and metro line 2 (Tan Van - Binh Duong New City) is available, there will be no need for this bus station.

TP.HCM: Phó chủ tịch Bùi Xuân Cường kiểm tra công trình giao thông, tháo gỡ ùn tắc- Ảnh 6.
The planned area for construction of metro station No. 2 in Binh Duong ward (HCMC)
PHOTO: DO TRUONG

Late in the afternoon, Vice Chairman Bui Xuan Cuong worked with Becamex IDC Corporation on the pre-feasibility plan for building metro line 2 from Tan Van intersection to Binh Duong ward (HCMC).

Source: https://ttbc-hcm.gov.vn/tp-hcm-pho-chu-tich-bui-xuan-cuong-kiem-tra-cong-trinh-giao-thong-thao-go-un-tac-1019264.html


Comment (0)

No data
No data
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together

Heritage

Figure

Business

No videos available

News

Political System

Local

Product