Nha Trang - Cam Lam Expressway before opening day

Báo Thanh niênBáo Thanh niên17/05/2023


The Nha Trang - Cam Lam Expressway is over 49 km long, started in September 2021 with a total cost of over VND 7,600 billion, implemented in the form of public-private partnership (PPP), BOT contract (build - operate - transfer). The project has a scale of 4 lanes, starting at Dien Tho commune, Dien Khanh district, ending at Cam Thinh Tay commune, Cam Ranh city.

The project invested by Son Hai Group Company Limited has been 3 months ahead of schedule.

Cao tốc Nha Trang - Cam Lâm trước ngày thông xe - Ảnh 1.

According to the plan, the Nha Trang - Cam Lam expressway will officially open to traffic on May 19. The inauguration ceremony of the project will be held later due to changes in the working program of the Government leaders.

Cao tốc Nha Trang - Cam Lâm trước ngày thông xe - Ảnh 2.

At the project, the construction units have basically completed the items and are ready to open traffic as planned.

Cao tốc Nha Trang - Cam Lâm trước ngày thông xe - Ảnh 3.

Workers are cleaning the road in preparation for the opening day.

Cao tốc Nha Trang - Cam Lâm trước ngày thông xe - Ảnh 4.

Mr. Nguyen Van Huy, Director of Nha Trang - Cam Lam Expressway Investment Company Limited (Son Hai Group), said that the project applied many modern technologies, especially the technology of constructing the median strip with cement concrete poured in one piece at the site using specialized German machines to help the concrete surface be smooth and free of cracks.

Cao tốc Nha Trang - Cam Lâm trước ngày thông xe - Ảnh 5.

To meet the inauguration schedule, about 1,700 engineers and workers worked day and night to complete the final items of the project.

Cao tốc Nha Trang - Cam Lâm trước ngày thông xe - Ảnh 6.

The final tasks such as installing signs, painting road markings... have been urgently completed by the contractor.

Cao tốc Nha Trang - Cam Lâm trước ngày thông xe - Ảnh 7.

Workers are installing the last rows of railings.

Cao tốc Nha Trang - Cam Lâm trước ngày thông xe - Ảnh 8.

Doc San Tunnel is one of the most important but also the most difficult to construct items of the Nha Trang - Cam Lam expressway project and has been completed.

Cao tốc Nha Trang - Cam Lâm trước ngày thông xe - Ảnh 9.

Recently, Mr. Nguyen Tan Tuan, Chairman of Khanh Hoa Provincial People's Committee, came to inspect the project to prepare for the opening day.

Cao tốc Nha Trang - Cam Lâm trước ngày thông xe - Ảnh 10.

Workers and engineers check the fire prevention and fighting system in Doc San tunnel.

Cao tốc Nha Trang - Cam Lâm trước ngày thông xe - Ảnh 11.

The entire Nha Trang - Cam Lam expressway is arranged with 18 emergency stops, with an emergency lane on each side at the end of the route. The expressway also has 25 bridges, including 10 overpasses, each bridge is 5-12 m wide depending on the connecting road.



Source link

Comment (0)

No data
No data

Same tag

Same category

Enjoy the top fireworks at the opening night of the 2025 Da Nang International Fireworks Festival
Da Nang International Fireworks Festival 2025 (DIFF 2025) is the longest in history
Hundreds of colorful offering trays sold on the occasion of the Duanwu Festival
Ninh Thuan's infinity beach is most beautiful until the end of June, don't miss it!

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product