At Component 2 Project invested by Management Board 85, the intersection between Bien Hoa - Vung Tau Expressway and Ho Chi Minh City - Long Thanh - Dau Giay Expressway has taken shape. Photo: Minh Tai |
 |
The bridges and access roads have gradually taken shape, creating a giant “asterisk” intersection. Of the three interconnecting intersections, the Long Thanh intersection has reached about 75% of the volume, the Long Thanh Airport intersection is almost complete, and the Tan Hiep intersection has reached 85% of the volume. Photo: Minh Tai |
 |
This is also the intersection with route T2 connecting to Long Thanh Airport. Photo: Minh Tai |
 |
 | According to Management Board 85, currently, Project Component 2 output has reached 2,308/4,279 billion VND, reaching 54%. Photo: Minh Tai |
 | Component 1 Project invested by Dong Nai Province Construction Investment Project Management Board includes 2 bid packages. Photo: Minh Tai |
 | Of which, package XL 18 (from Km0+000-Km6+200) is organizing 18 construction sites, with output reaching 414.4/1,261 billion VND (32.85%). Photo: Minh Tai |
 | Package XL 21 (from Km6+200-Km16+000) is organizing 17 construction sites, with output reaching 637/1,236 billion VND (50%). Photo: Minh Tai |
 |  | Recently, the Dong Nai Province Construction Investment Project Management Board said that some contractors have not met the schedule. Photo: Minh Tai |
 | According to plan, by December 19, 2025, the Bien Hoa - Vung Tau Expressway Project will be technically open to traffic. Photo: Minh Tai |
|
|
Xuan Luong - Minh Hanh - Minh Tai