According to the Vietnam Airports Corporation (ACV - the investor), currently at the Long Thanh airport construction site, construction is underway on three major items: the passenger terminal; runways, taxiways, aprons; and two connecting roads from the outside to the airport (T1 and T2).
Entrance gate to Long Thanh airport construction site
Currently, after more than 5 months of construction, the project has basically met the set schedule. At the large construction site, there are nearly 4,000 domestic and international engineers and workers along with nearly 2,000 machines, vehicles and equipment; the construction teams are also deployed to the maximum, working continuously day and night with the highest goal of speeding up the progress.
Contractors will speed up construction this dry season to speed up progress.
To ensure the progress of the Long Thanh airport project, contractors accelerated the progress during the peak 6-month dry season, and also worked through Tet. And during the 2024 Lunar New Year, there were about 1,000 workers and 100 machines working through Tet at the construction site.
Runway and lotus-shaped terminal behind
Mr. Duong Quang Dien, Permanent Deputy Director of Long Thanh Airport Project Management Board, added that the 6-month dry season is a favorable weather condition to maximize progress.
It is currently the dry season, the weather is favorable to speed up the progress.
Therefore, ACV has directed contractors to focus all their efforts, increase the number of human resources, machinery, and work overtime day and night from 7am to 11pm. Field offices are always on duty 24/7 to urge and handle problems arising during the construction process.
Night shift construction at Long Thanh airport construction site
Contractor wishes and encourages engineers and workers to work through Tet
"During the Tet holiday, ACV has directed contractors to complete the construction plan during Tet and deploy personnel and equipment to ensure close adherence to the progress of each item in particular and the overall progress of the project in general. Along with that, ACV has instructed units to arrange to take care of the lives of all employees, so that everyone can have a warm and complete spring," said Mr. Duong Quang Dien.
The air traffic control tower, considered the "brain" of Long Thanh airport, is also busy with construction, working through Tet.
The tallest air traffic control tower in Vietnam with 120 m
The air traffic control tower project, invested by Vietnam Air Traffic Management Corporation, started construction in September 2022 by the joint venture of 36 Corporation - Newtatco - VNCC. To ensure the project is completed on schedule, Vietnam Air Traffic Management Corporation launched a 150-day and night competition at the construction site with the spirit of "overcoming the sun, overcoming the rain", working in "3 shifts and 4 shifts", working through holidays and Tet, especially during the Lunar New Year and the dry season of 2024, ensuring productivity, quality, efficiency, and exceeding the set targets, contributing to accelerating the construction progress to bring the project to the finish line on time and ahead of schedule.