Ea Kar District agrees on the method of handing over the land for the Khanh Hoa - Buon Ma Thuot Expressway Project

Báo Đắk LắkBáo Đắk Lắk17/06/2023


21:25, 17/06/2023

Ea Kar District People's Committee said that the Khanh Hoa - Buon Ma Thuot Expressway Project passes through Ea Kar District with a total length of 13.5 km, the area cleared for construction of the entire route is about 104 hectares.

Implementing the direction of the Provincial People's Committee, Ea Kar district has coordinated with relevant agencies and units to conduct propaganda, mobilization, and site clearance to hand over the compensated and supported sites to investors before June 30, 2023 with the site volume of over 70%.

Up to now, Ea Kar district has implemented the committed progress of site clearance and agreed on the time, method and volume of handover with the investors.

hfghgfh
Leaders of the Ea Kar District Party Committee's Propaganda Department (left cover) grasp the situation of land clearance work for the Khanh Hoa - Buon Ma Thuot Expressway Project in Cu Elang commune (Ea Kar district).

Specifically, for Component Project 2 (Party 6, Ministry of Transport as the investor), it was agreed to hand over 2 phases including: phase 1 handover of the site area of 10.9 hectares on June 16, 2023, phase 2 handover of the site area of 9.6 hectares on June 22, 2023.

For Component Project 3 (Provincial Traffic Construction Investment and Rural Development Project Management Board is the investor), it is agreed to hand over 5 phases including: phase 1 handover of the site area of 4.3 hectares on June 16, 2023, phase 2 handover of the site area of 21.2 hectares on June 20, 2023, phase 3 handover of the site area of 24 hectares on June 25, 2023, phase 4 handover of the site area of 17 hectares from June 28 to June 30, 2023, the final phase handover of the site area of 17.19 hectares on July 30, 2023.

After receiving the handover, the investors are responsible for presiding over and coordinating with the People's Committees of the communes and Ea Kar Forestry One Member Co., Ltd. to manage the site, not to allow re-encroachment. If any problems arise beyond their authority, they must promptly report to the District People's Committee for coordination and resolution. At the same time, before starting construction, the investors are responsible for making plans for progress, time, human resources, means of construction, etc., and reporting to the Ea Kar District People's Committee 7 days in advance so that the District People's Committee can direct the coordination of relevant parties and ensure security and order.

Nguyen Xuan



Source link

Comment (0)

No data
No data
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?
Taste of the river region

Heritage

Figure

Business

No videos available

News

Political System

Local

Product