The Department of Construction has just submitted a report to the grassroots appraisal council on the appraisal of the Feasibility Study Report for the investment project to build Dinh Khao bridge connecting the two provinces of Vinh Long and Ben Tre (old) under the public-private partnership (PPP) method. It is expected that by July 20, the grassroots appraisal council will review and submit for approval the Feasibility Study Report of the project, announcing the Dinh Khao bridge project under the PPP form.
However, according to the Department of Construction, the Dinh Khao bridge project is the first project in the province to be invested in the form of PPP, so the departments and localities do not have experience. At the same time, the relevant legal documents at this time are constantly changing, so it takes time to study, leading to some prolonged work. The work of completing the dossier according to the appraisal content still has many problems, leading to the need to explain, clarify, and complete many times...
In addition, the site clearance work in Vinh Long province has about 78 households affected by the complete clearance. Currently, the units are completing the feasibility study report for the residential area, resettlement and social housing project in Mang Thit district (old) and must be completed before the decision to reclaim the land is made... Therefore, the approval of the site clearance plan for the investment project to build Dinh Khao bridge under the PPP method will not be possible to start the project before August 19 as planned.
The Department of Construction proposed that, since the Provincial People's Committee has now established the Vinh Long Provincial Transport Project Management Board, the Department recommends that the Provincial People's Committee assign this board to carry out the next steps of the project after the project is approved. At the same time, it recommends that the Vinh Long Provincial People's Committee assign the Department of Finance to preside over and coordinate with relevant departments and units to urgently study and draft a PPP contract to implement the Dinh Khao Bridge project, because this is the basis for organizing the selection of investors.
KHANH DUY
Source: https://baovinhlong.com.vn/thoi-su/202507/kien-nghi-lui-thoi-gian-khoi-cong-du-an-cau-dinh-khao-8903638/
Comment (0)