Households in Cam Hung commune, Cam Giang district, Hai Duong province attend the dialogue conference on the construction of 220kV power line on June 29. (Source: Nhan Dan Newspaper) |
The 220kV Hai Duong Thermal Power Plant - 500kV Pho Noi Station transmission line project passes through 5 communes and towns in Cam Giang district with a total of 59 poles, including: Cam Dong commune 16 poles, Tan Truong commune 29 poles, Kim Giang commune (now Cam Giang town) 6 poles, Thach Loi commune 5 poles, Cam Hung commune 3 poles.
Up to now, the Resettlement Compensation and Support Council has completed site clearance and handed over all pole foot locations to the Northern Power Project Management Board to construct and wire all pole foot locations.
The 220kV Hai Duong Thermal Power Plant - 500kV Pho Noi Station Transmission Line Project according to the approved design includes 2 circuits on the current pole, and has completed pulling circuit 1 (8 wires/1 pole) when implementing the 500kV Pho Noi Transformer Station project and connecting lines through Cam Hung commune since 2019.
This is an important project of the State and the province to serve the socio -economic development of the country in general and Hai Duong province in particular.
Hai Duong Provincial Party Secretary Tran Duc Thang inspects the situation in Cam Hung commune, Cam Giang. (Source: Hai Duong Provincial Party Committee) |
In order to support the smooth implementation of the project, the People's Committee of Cam Giang district has implemented compensation and support when clearing the project site in accordance with state regulations and mechanisms permitted by the Provincial People's Committee; received opinions and reported to the Provincial People's Committee to resolve all opinions and recommendations of households, specifically on the level of compensation and support.
Listening to people's opinions, Cam Giang District People's Committee coordinated with Cam Hung Commune People's Committee and the Northern Power Project Management Board to organize 3 meetings with households and individuals located under the 220kV power line corridor on April 24, June 9 and June 27.
On that basis, on July 4, the District People's Committee developed Plan No. 93/KH-UBND to ensure security and order to support the construction of the power line of the Hai Duong Thermal Power Plant 220kV Power Line - Pho Noi 500kV Station Investment Project (Section through Dong Xuyen village, Ho Ve village and Dong Dong village, Cam Hung commune).
The plan clearly states the purpose, requirements, situation assessment, assignment of tasks to specific forces and means, and indicates the steps to support the construction, implementation costs, plans to handle some possible situations and assigns the implementation organization to ensure security and order to support the construction of the power line extension of the Hai Duong Thermal Power Plant 220kV Power Line - Pho Noi 500kV Station Investment Project (Section through Dong Xuyen village, Ho Ve village and Dong Dong village, Cam Hung commune).
220kV line running through Cam Hung commune. (Source: Thanh Nien) |
With the attention of leaders at all levels along with the efforts to implement methodically and organizedly, meeting the aspirations of the people and the requirements of the project, we believe that the construction process of extending the power line of the Hai Duong Thermal Power Plant 220kV Power Line - Pho Noi 500kV Station (Section through Dong Xuyen village, Ho Ve village and Dong Dong village, Cam Hung commune) will ensure order and progress according to the direction of the Provincial Party Committee and Provincial People's Committee, while maintaining strict discipline and ensuring fairness in site clearance.
Thereby, contributing to the completion of the task of connecting the power line to the common grid to serve national interests and socio-economic development.