Attending the meeting were representatives of leaders of relevant departments, branches and sectors, leaders of People's Committees of communes and the Investment Project Management Board of Di Linh and Duc Trong areas.

The working session focused on reviewing the difficulties and obstacles that are hindering the progress of disbursement of public investment capital in these two areas. The goal is to find specific and practical solutions to speed up the implementation of projects, ensuring that capital is used effectively, serving the socio-economic development of the locality.

According to the report from the Di Linh Area Construction Investment Project Management Board, the unit is currently managing 78 projects, including projects using capital from the central budget, provincial budget and district budget (old). The total capital allocated is nearly 260 billion VND and to date, the disbursement rate has reached 47.49% of the plan, equivalent to 122,543 billion VND.
Meanwhile, the Duc Trong Area Construction Investment Project Management Board No. 1 reported that the total planned capital allocation for 2025 is 308,318 billion VND for 38 projects. It is estimated that up to now, more than 129,360 billion VND has been disbursed, reaching a rate of 42%.

The disbursement rate by capital source shows that the central budget reached 66.8%, the provincial budget reached 6.6% and the district budget reached 50.3%.
Particularly for the project to renovate and upgrade National Highway 28B, the total allocated capital is 30,121 billion VND, of which 3,184 billion VND has been disbursed, reaching a rate of 10.6%.

The leaders of the Duc Trong Area Construction Investment Project Management Board also pointed out a number of projects that are unlikely to be disbursed this year, such as the Ta Hoét Reservoir Resettlement Infrastructure Construction Project and the Pre Landfill.

At the meeting, representatives of localities also reported on the disbursement of public investment capital in their localities. Localities also frankly pointed out the difficulties in disbursing public investment capital, mainly related to site clearance work, due to some households not agreeing or complaining.
The leaders of the People's Committees of the communes also pledged to strengthen coordination with the Project Management Board, promote mobilization and persuasion of people, and create consensus in site clearance work to implement important projects in the area.

Leaders of departments and branches also made assessments and recommendations to improve capital disbursement and promote project progress.
.jpg)
Vice Chairman of Lam Dong Provincial People's Committee Vo Ngoc Hiep requested departments, branches and sectors to seriously implement the province's instructions after field inspections and meetings to remove previous difficulties and obstacles, promptly resolve problems, create favorable conditions for localities and investment project management boards to speed up disbursement progress. Especially for the guidance on land unit prices and crop compensation.
Disbursement of public investment capital is an important task that needs to be carried out proactively, seriously and urgently to promote the socio-economic development of the province.
Vice Chairman of Lam Dong Provincial People's Committee Vo Ngoc Hiep

Communes and Construction Investment Project Management Boards must set a target of disbursing 100% of public investment capital for 2025 this year. On that basis, for projects that are still facing difficulties, it is necessary to set up weekly and monthly progress schedules and assign staff to monitor specific implementation to achieve progress.
In particular, he emphasized that the People's Committees of communes need to further promote the sense of responsibility in mobilizing people in compensation work, and do a good job of informing and providing information about projects to people. Resolutely carry out compensation for households that deliberately do not hand over the land without legal basis.
He also requested localities to pay attention and coordinate well in compensation work, site clearance, and resettlement area construction for the expressway project.
Source: https://baolamdong.vn/quyet-tam-thao-go-vuong-mac-tang-toc-giai-ngan-von-dau-tu-cong-392240.html