
Road construction in the province is under construction.
The Provincial People's Committee has issued many documents directing and urging investors and relevant departments and branches to resolutely implement measures to ensure timely disbursement progress, aiming to complete 100% of the annual plan.
Accordingly, investors are required to develop detailed plans for weeks and months; report disbursement results weekly for the Provincial People's Committee to monitor, promptly direct, and report to the Provincial Party Committee and the Central Government when exceeding their authority. The target is that by the end of the fourth quarter of 2025, the disbursement rate will reach over 95% of the plan and by the end of the year, it will reach 100%.
Regarding capital, the Prime Minister has allocated more than VND 16,298 billion of state budget capital for Tay Ninh in 2025. The Provincial People's Council has allocated a total of VND 17,123 billion, including the allocated central capital and the additional provincial budget of nearly VND 825 billion. The Provincial People's Committee has so far allocated almost all of the capital, with only about VND 670 million remaining unallocated due to a number of unapproved projects, expected to be completed in December 2025.
As of November 20, 2025, the total disbursement value reached more than VND 11,556 billion, equivalent to 70.9% of the plan assigned by the Prime Minister and 67.5% of the plan allocated by the Provincial People's Committee. Of the 33 investors, 8 investors disbursed over 75% of the plan; 15 investors disbursed from 50% to 75%; the remaining 10 investors disbursed less than 50%, of which 5 investors have not disbursed.
Despite positive results, this year's disbursement rate is still lower than the same period last year and expectations, mainly due to a number of objective difficulties. The implementation of two-level local government took a long time to adjust procedures and review data handover; site clearance work still encountered difficulties; there was a lack of construction materials at some points; along with adverse weather effects.
According to the assessment of the Provincial People's Committee, the effective disbursement of public investment capital sources not only promotes the progress of key projects but also creates a strong driving force for sustainable socio -economic development in the coming years. This also contributes to affirming the determination of Tay Ninh province in improving the efficiency of management and use of public investment capital, towards the goal of synchronous and sustainable development./.
Le Duc
Source: https://baolongan.vn/tay-ninh-tang-toc-giai-ngan-von-dau-tu-cong-nam-2025-a207256.html






Comment (0)