The project "Construction of traffic roads to the center of Nhon Mai and Mai Son communes, Tuong Duong district" is considered a major project, not only specific to Nghe An province, but also a target list for the National Target Program on Socio-Economic Development of Ethnic Minority and Mountainous Areas, Phase I: From 2021-2025 nationwide. However, this major project is difficult to complete on schedule due to many difficulties. On the morning of November 19, the People's Committee of Quang Tri province solemnly organized the 4th Congress of Ethnic Minorities, 20024. With the theme "Ethnic groups of Quang Tri province unite, innovate, promote advantages, potentials, integrate and develop", the Congress is an important political event, a great solidarity day of more than 21,000 ethnic minorities in the heroic homeland of Quang Tri. From the 2021-2022 school year up to now, hundreds of teachers in Ha Long city (Quang Ninh) have written volunteer applications to work with schools and classes in ethnic minority and mountainous areas. The rotation of teachers from schools in favorable areas to highland areas has added motivation and new spirit, helping students in difficult areas have the opportunity to access many teaching methods of teachers in the center; At the same time, it will solve the problem of surplus teachers in favorable areas and shortage of teachers in difficult areas. From July 1, 2025, when employees retire and have paid compulsory social insurance for 15 years or more, they will receive a pension if they reach the retirement age according to the provisions of the Labor Code. In addition to pensions, workers also receive a one-time subsidy upon retirement. On the morning of November 19, Quan Ba district, Ha Giang province opened the Conference: Training, coaching, and fact-finding to serve the work of information and propaganda to raise national awareness and responsibility for protecting the Fatherland's borders in Quan Ba district in 2024. On the morning of November 19, the People's Committee of Quang Tri province solemnly organized the 4th Congress of Ethnic Minorities in 20024. With the theme "Ethnic groups of Quang Tri province unite, innovate, promote advantages, potentials, integrate and develop", the Congress is an important political event, a great solidarity day of more than 21,000 ethnic minorities in the heroic homeland of Quang Tri. Implementing Project 9, the National Target Program on socio-economic development of ethnic minority and mountainous areas in the period 2021 - 2030, phase I: From 2021 - 2030, phase I: From 2021 - 2030, the People's Committee of Quang Tri province solemnly organized the 4th Congress of Ethnic Minorities in 2021 - 2030. 2021 - 2025 (abbreviated as National Target Program 1719), the Kon Tum Provincial Ethnic Minorities Committee has coordinated with the Department of Education and Training to organize many communication campaigns integrating gender education content in schools to raise awareness for students and parents about the harmful effects of early marriage and consanguineous marriage (TH&HNCHT). Implementing Project 6, National Target Program on socio-economic development in ethnic minority and mountainous areas for the period 2021 - 2030, phase I: From 2021 - 2025, on the morning of November 19, in Dak To district (Kon Tum), the Department of Cultural Heritage (Ministry of Culture, Sports and Tourism) coordinated with the Department of Culture, Sports and Tourism of Kon Tum province to organize a training course, fostering professional skills, teaching intangible culture and implementing a model of connecting intangible cultural heritage "Art of making and customs of using bamboo musical instruments" Xo Dang and Gia Rai people" in the Kon Tum - Gia Lai heritage tourism journey. The summary news of the Ethnic and Development Newspaper, on November 18, has the following notable information: Great Ethnic Solidarity Week - Vietnam Cultural Heritage 2024. Discovery of new plant species in Dakrong Nature Reserve. Sinh ca artist in Gieng Do village. Along with other current news in ethnic minority and mountainous areas. With many good and creative ways, the Party Committee and government of Dong Hy district (Thai Nguyen province) have mobilized resources to support poor households and policy households to repair and build new houses, helping them have more confidence and motivation to rise out of poverty. Phuoc Son is a mountainous district of Quang Nam province, with the majority of Gie - Trieng people living. In order for the villages and hamlets of the people to become more prosperous, in addition to the efforts of the authorities at all levels and the people, the prestigious people have also made practical and effective contributions. They are always pioneers in many fields, actively propagating and mobilizing everyone to join hands to build the homeland, develop the economy, and stay away from backward customs. Doctors and nurses of Phu Tho General Hospital have just saved the life of a 7-year-old child in Nong Trang ward, Viet Tri city who was caught in a rolling door around the neck, leading to circulatory arrest. This is one of the patients saved from the "doctor-to-people model" deployed since October 2023. In the 3 years from 2022 to 2024, Ninh Thuan province focuses on implementing the National Target Program on Socio-Economic Development in Ethnic Minority and Mountainous Areas for the 2021-2030 period according to Decision No. 1719/QD-TTg dated October 19, 2021, of the Prime Minister (abbreviated as National Target Program 1719). The program has created livelihoods for people to effectively promote investment resources and rise out of poverty sustainably. At the same time, investing in infrastructure construction will contribute significantly to comprehensively improving the lives of ethnic minorities and mountainous areas. On the morning of November 19, Lang Son province organized the 4th Provincial Congress of Ethnic Minorities in 2024. Member of the Party Central Committee, Minister, Chairman of the Ethnic Committee Hau A Lenh attended and delivered a speech directing the Congress.
The project "Construction of traffic roads to the center of Nhon Mai and Mai Son communes, Tuong Duong district" is the largest project using capital from the National Target Program on Socio -Economic Development of Ethnic Minority and Mountainous Areas, Phase I: 2021-2025 (National Target Program 1719), accounting for 12% of the total development investment capital for the period 2021-2025.
From a macro perspective, this is a specific list not only for Nghe An province, but also a list of indicators for the National Target Program 1719 nationwide. Currently, the traffic project has a major responsibility, which is to open new roads to commune centers for communes that do not have roads from the district center to the commune center.
The project has a total investment of 428.8 billion VND, including 16 packages. Of which, the 2 largest packages are Package XL02 for construction of the section Km8+877.68 - Km12+713 and the Suoi Hoc, Cha Lai 1, Cha Lai 2 bridges (package price 281.6 billion VND) and Package XL01 for construction of the section Km0+00 - Km8+877.68 (99.79 billion VND).
This project is part of the goal of developing the transport infrastructure network, aiming at socio-economic development, ensuring national defense and security; contributing to poverty reduction in the district and connecting the center of Nhon Mai and Mai Son communes through Huu Khuong commune (communes in the Ban Ve hydropower reservoir area) to the center of Tuong Duong district.
Mr. Lo Van Giap, Chairman of the People's Committee of Huu Khuong Commune (Tuong Duong) informed: For a long time, the communes in the lake area including Huu Khuong, Nhon Mai, Mai Son have had many difficulties and hardships due to the lack of roads to the district center. These three communes want to trade with the outside, there are only two ways: by boat on the lake for more than 2 hours or borrow a road through Ky Son district, with a length of 180km. Agricultural products are very difficult to sell, so people's lives are heavily self-sufficient. When the project started, people were very excited because after completion, the deadlock of the communes in the lake area would be broken.
The project has been taking the first steps of investment and construction, but has encountered many difficulties and obstacles. According to the report of the Nghe An Department of Transport - the investor, there are still some difficulties and obstacles affecting the construction progress as well as the disbursement of capital sources that are difficult to ensure as required, leading to the general disbursement rate of the National Target Program 1719 in the locality being low.
The representative of the Project Management Board of Nghe An Department of Transport said: The common difficulty when implementing the project is that the mountainous area is remote, has high hills, and difficult terrain. This leads to many difficulties in implementing the work at the site, such as transporting machinery, equipment, supplies, and materials. The construction unit had to transport supplies and equipment by ferry and boat, which was very costly and difficult.
Another factor that also affects the overall progress of the project is the waiting time for the completion of the environmental impact assessment procedure, which lasted 6 months. Specifically, on November 13, 2023, the Nghe An Department of Transport submitted the project to the Ministry of Natural Resources and Environment for appraisal; but it was not until May 27, 2024 that the Ministry of Natural Resources and Environment approved it.
Notably, most of the projects are implemented on protected forest land, so it takes a lot of time to convert land use and forest purposes. Therefore, the time to carry out site clearance is long and requires many steps and procedures from related units, leading to slow handover of the site to the construction contractor.
Through our research, there are many other factors affecting the construction progress of this project. The Suoi Hoc bridge component project, a level I project located in the Ban Ve hydroelectric reservoir, is facing a disadvantage due to the water level being constantly high, leading to the construction unit only being able to carry out the lower part for about 4 months during the dry season (from April to July). Meanwhile, the construction unit cannot mobilize large equipment such as barges and bored pile drilling machines into the reservoir to speed up the progress.
As a beneficiary, Tuong Duong district is also very "frustrated" when the investment and construction procedures are prolonged, leading to delays in people's benefits. Chairman of Tuong Duong District People's Committee - Mr. Dinh Hong Vinh shared: We really hope that the Project will be completed soon, put into use, serving the travel, production and trading needs of people in the communes in the reservoir area, which are currently facing difficulties. With the current progress, the Project will not be completed by the end of the 2021-2025 period.
With the current difficulties and construction progress, the project to open new roads to commune centers for communes that do not have roads from the district center to the commune center will be difficult to complete as planned. Thus, the target and goal by 2025, 100% of communes have car roads to the commune center of the district will not be possible to achieve.
Source: https://baodantoc.vn/thuc-hien-dai-du-an-tu-nguon-von-chuong-trinh-mtqg-1719-o-tuong-duong-vap-nhieu-cai-kho-1731849946579.htm