On the morning of April 15, the People's Committee of Thanh Hoa province had a working session with the Vietnam Electricity Group (EVN) to resolve difficulties and obstacles in implementing investment projects to build the power transmission grid in Thanh Hoa province. Comrade Do Minh Tuan, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee and Comrade Dang Hoang An, Chairman of the Board of Members (BoD) of EVN co-chaired the meeting.
Overview of the working session.
Attending the meeting were leaders and representatives of EVN's specialized departments and agencies, the National Power Transmission Corporation. On the Thanh Hoa side, there was comrade Mai Xuan Liem, member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee, and representatives of departments, branches and functional units.
Delegates attending the meeting.
According to EVN's report at the working session, implementing the tasks assigned by the Prime Minister and the Ministry of Industry and Trade, EVN and functional units are currently implementing power grid projects in Thanh Hoa province such as: 500kV line of Nam Dinh I Thermal Power Plant - Thanh Hoa; 500kV line of Quynh Luu Thermal Power Plant - Thanh Hoa; 500kV Thanh Hoa transformer station; 220kV line of Nam Sum - Nong Cong; 220kV transformer station of Nghi Son Economic Zone. These projects are under construction. In addition, there are a number of projects in the investment preparation stage such as: 220kV line of Nghi Son Thermal Power Plant - Nong Cong - Quynh Luu branch; 220kV Sam Son transformer station and 220kV line of Thanh Hoa - Sam Son; 220kV Hau Loc transformer station...
Representative of National Power Transmission Corporation speaking at the meeting.
According to EVN representative, besides the achieved results, there are still some difficulties and problems regarding compensation for site clearance and conversion of forest land use purposes that have not been completely resolved, affecting the progress of completing the energization of projects as planned, especially the 220kV Nam Sum - Nong Cong transmission line project. This project has a transmission line passing through the districts of Nhu Xuan, Nhu Thanh and Nong Cong with a total length of 52.14km, including 125 pole foundation locations and 47 anchor intervals. Currently, 9/125 pole foundation locations (in Nhu Xuan district) and 24/47 anchor intervals have not been handed over (of which Nhu Xuan district has 7/19 anchor intervals, Nhu Xuan has 17/20 anchor intervals).
Representative of the Northern Power Project Management Board speaking at the meeting.
At the conference, delegates focused on discussing many issues related to land acquisition, land use conversion of natural forests; compensation for households planting trees on land that is not allocated, or whose land use contracts have expired... for the 220kV Nam Sum - Nong Cong transmission line project; the current situation of resolving issues for households with residential land, houses, and structures located within the corridor of the 500kV Nam Dinh I - Thanh Hoa transmission line project; the issue of changing the purpose of rice-growing land for the 500kV Thanh Hoa transformer station project...
Director of the Department of Agriculture and Rural Development Cao Van Cuong spoke at the meeting.
Vice Chairman of the Provincial People's Committee Mai Xuan Liem spoke at the meeting.
Based on the report content as well as through discussions of delegates, Chairman of the Provincial People's Committee Do Minh Tuan gave specific instructions and assigned tasks to the provincial sectors and localities to proactively resolve difficulties and problems for each project.
Regarding the construction of the 220kV Nam Sum - Nong Cong line, the Chairman of the Provincial People's Committee requested the Northern Power Project Management Board to determine the direction of the temporary construction route through natural forests; coordinate with the forest rangers and local authorities to determine the number of trees that need to be cut down to develop a compensation plan.
Chairman of the Provincial People's Committee Do Minh Tuan spoke at the meeting.
Assign Như Thanh district to urgently approve the compensation plan for 31 households planting trees on land without a contract or the contract has expired, to hand over the entire site to the investor. Như Xuân district urgently issues a decision to reclaim land, approves the compensation plan and hands over the site of natural forest land immediately after the Provincial People's Committee approves and the investor completes the payment for reforestation. At the same time, propagate and mobilize households in the district to agree with the plan and receive compensation according to the approved decision.
For the 500kV Nam Dinh I - Thanh Hoa Power Line Project, the Chairman of the Provincial People's Committee assigned localities and related units to effectively implement the work of clearing and relocating households with residential land, houses, and structures within the line corridor.
The Chairman of the Provincial People's Committee also gave specific comments on EVN's proposal regarding the conversion of rice-growing land use purposes to implement the Thanh Hoa 500kV Transformer Station Project...
Chairman of the Provincial People's Committee Do Minh Tuan emphasized: The power transmission grid projects deployed in Thanh Hoa province are being effectively implemented by EVN and the National Power Transmission Corporation. In particular, the 500kV Nam Dinh I - Thanh Hoa Thermal Power Plant transmission line project has been and is being implemented according to the plan and schedule.
Chairman of the Provincial People's Committee Do Minh Tuan spoke at the meeting.
The Chairman of the Provincial People's Committee stated: The implementation time of the projects is very urgent, so it is inevitable that there will be difficulties and problems. However, with the active participation and close coordination between EVN and Thanh Hoa province and the sectors and localities of the province, the difficulties and problems will be gradually resolved.
The Chairman of the Provincial People's Committee affirmed: Thanh Hoa province always makes every effort together with EVN to successfully complete the tasks assigned by the Prime Minister and the Ministry of Industry and Trade. Thanh Hoa Provincial People's Committee has also assigned relevant departments and branches to continue to closely monitor and coordinate with relevant units of EVN to review and remove difficulties and obstacles to speed up the implementation of projects according to plan.
On behalf of EVN, Chairman of the Board of Directors Dang Hoang An thanked the close and timely attention of Thanh Hoa provincial leaders, departments, branches and localities of Thanh Hoa province for the power grid projects being implemented by EVN in the province.
EVN Chairman Dang Hoang An said that Thanh Hoa is the locality with the third highest electricity consumption demand in the Northern region, so EVN will strive to invest and complete projects according to plan to ensure power supply, meet production and business needs, and serve the socio-economic development goals of the province in particular and the country in general.
EVN Chairman of the Board of Directors Dang Hoang An spoke at the meeting.
EVN Board of Directors Chairman Dang Hoang An emphasized the spirit and high responsibility of Thanh Hoa province, all levels and sectors in the province in coordinating with EVN to implement projects and hoped that the close and effective coordination between Thanh Hoa province, EVN and functional units would continue to be promoted. At the same time, he stated: The 500 kV line project, circuit 3, from Quang Trach (Quang Binh) to Pho Noi (Hung Yen) has a completion date before June 30, 2024, the remaining time is not much, while the workload is very large. Therefore, EVN hopes to continue to receive the coordination and support of local authorities and the consensus of the people during the project construction process.
For the 220kV Nam Sum - Nong Cong transmission line project, EVN Chairman Dang Hoang An requested the Northern Power Project Management Board to submit a plan to determine a temporary route through the natural forest to the pole foundation location by April 23, 2024 at the latest, and propose local approval for early implementation of construction.