The Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board) has just sent a report to the Department of Construction, reflecting the difficulties and obstacles in the process of implementing investment projects under the form of public-private partnership (PPP) and BOT contracts in the city.
According to the report, the Transport Committee is assigned to be the investor, preparing investment in a number of BOT projects implemented under the specific mechanism of Resolution No. 98/2023/QH15 of the National Assembly .
Currently, the projects are in the stage of selecting survey consultants and preparing feasibility study reports, expected to be submitted to competent authorities for approval in the third quarter of 2025. However, the implementation process is facing many obstacles related to planning, site clearance and resettlement.
Binh Tien bridge and road project is currently facing problems related to adjusting the 1/2000 zoning plan. |
In the project to renovate and upgrade National Highway 22 through Hoc Mon district (old), the proposed project boundary with a cross-section of 60 m does not coincide with the 60 m road boundary in the current 1/2000 scale zoning plans, so the planning must be adjusted. In addition, because the basic design has not been approved, the specific project boundary cannot yet be determined.
At the National Highway 1 upgrade and expansion project (from Kinh Duong Vuong Street to the new Tay Ninh provincial border), site clearance work through Binh Chanh district (old) is facing serious difficulties due to the lack of land and apartments to resettle 1,400 affected households.
The North-South axis road upgrade project (from Nguyen Van Linh street to Ben Luc - Long Thanh expressway) is also facing difficulties in adjusting the planning because the district level has been removed because previously the local planning adjustment was carried out by the district level.
In this project, there is still an area of about 800 m² that overlaps with the Ben Luc - Long Thanh expressway project. This area is within the compensation scope of the expressway project but up to now, the Vietnam Expressway Corporation (VEC) has not yet implemented compensation according to the approved plan.
Also facing planning problems is Component 2 Project (construction of the bridge and main road), Binh Tien bridge and road. In this project, the local adjustment of the 1/2000 zoning plan as required must be completed by June 2025, but so far only District 6 (old) has met the schedule, while District 8 (old) and Binh Chanh district (old) are expected to be completed by the third quarter of 2025, affecting the overall progress of the project.
These are projects implemented according to the specific mechanisms and policies for the development of Ho Chi Minh City in Resolution No. 98/2023/QH15 of the 15th National Assembly.
Source: https://baodautu.vn/tphcm-mot-so-du-an-bot-dau-tu-theo-co-che-dac-thu-cua-nghi-quyet-98-van-chua-thong-d330633.html
Comment (0)