The investment project to build the right branch of Highway 382B and the project to upgrade and renovate the left branch of Highway 382B from Km2+350 to Km14+420 are key investment projects in Viet Yen commune (Hung Yen). When completed, they will facilitate trade and develop the local socio -economy. Therefore, in recent times, local authorities have actively led, directed, and coordinated with relevant agencies to do a good job of site clearance (GPMB) to serve the construction of projects, ensuring publicity, democracy, and compliance with procedures and regulations of the law.
Road DT.382B right branch has completed site clearance for construction.
Currently, the right branch of DT.382B road through Viet Yen commune has completed the entire site clearance for construction. 6 households whose land is recovered and are eligible for resettlement are urgently completing their documents to hand over the land to the people.
Construction on DT.382B right branch.
For the left branch of DT.382B, there are a total of 251 households whose land within the project area was recovered for site clearance with a total area of 4.43ha; of which, 25 households have residential land recovered. The agricultural land area has basically been counted, and the residential land is being counted.
Current state of degradation of DT.382B left branch.
Mr. Hoang Van Dung, Party cell secretary and head of My Xa village, shared: The village Party Committee and government have disseminated the project implementation policy to all Party members and people; at the same time, assigned tasks to Party members in charge of residential areas to regularly follow the area to grasp the thoughts and aspirations of the people. The village organized propaganda teams to households whose land was recovered to propagate and mobilize people to support the policy and actively cooperate in counting and reviewing the origin of the land. The people in the village highly agreed with the project and always created conditions for units to conduct reviews, counting, and make plans for land recovery. However, the project is being delayed due to the province. The unit price for compensation and support for crops and assets on agricultural land has not been issued. People want the project to be quickly implemented because the road has seriously degraded and is unsafe to travel on.
The entire 337 square meters of residential land of Ms. Nguyen Thi Huong's family in Luc Dien village was confiscated to serve the investment in the construction of the left branch of DT.382B road.
Along with the concerns of households whose agricultural land was recovered, households whose residential land was recovered are also worried. Ms. Nguyen Thi Huong, Luc Dien village said: My family has 337m2 of residential land that was confiscated to serve the investment project to build the left branch of DT.382B road. This means that my family's entire residential land area was confiscated and we had to move to another place according to the resettlement policy. My family has lived here for many years and is doing business on this land, so when it is confiscated and moved to a new place, we do not know what our work and life will be like. However, I still support the State's policy on building roads, so that the roads are no longer muddy, full of potholes, so that people can travel conveniently and safely, promoting local socio-economic development. However, people hope that the State will have appropriate policies to soon stabilize their lives.
Viet Yen commune officials propagate and disseminate land recovery policy to Ms. Nguyen Thi Huong's family, Luc Dien village, Viet Yen commune.
With the desire to speed up the construction progress of projects, immediately after operating the 2-level local government model, the People's Committee of Viet Yen commune reviewed, inspected, and re-evaluated the entire progress and results of site clearance to have a plan to advise and organize implementation. Comrade Nguyen Van Dung, Chairman of Viet Yen Commune People's Committee said: This are key projects, so Site clearance work is always given top priority. Difficulties and obstacles arising from mechanisms and policies will continue to be reported to the locality and recommended to the province for solutions. At the same time, the Party Committee and the communal government will continue to promote information and propaganda work to disseminate the policies of the Party, the State and the province to all the people, creating consensus and support for early handover of the site for construction.
Mai Nhung