Ensure to complete the peak campaign of public investment disbursement in 2025 by December 31

On the afternoon of October 18, 2025, the Department of Construction held a conference to implement the peak campaign to complete the disbursement of public investment capital in 2025, with the participation of leaders of project management boards, construction units and leaders of the People's Committees of 14 communes and wards where the project passes.

Sở Xây dựng tỉnh Thanh HóaSở Xây dựng tỉnh Thanh Hóa18/10/2025

English: The news

Conference scene.

Implementing the tasks assigned by the Provincial People's Committee, the Department of Construction issued Plan No. 50/KH-SXD dated October 13, 2025 on implementing the peak campaign to complete the disbursement of public investment capital in 2025 for projects invested by the Department.

Accordingly, in 2025, the Department of Construction was assigned by the Provincial People's Committee to be the investor of 25 projects with a total capital of VND 2,458,028 billion.

To date, 302,232 billion VND has been disbursed. Excluding the capital proposed for transfer, by the end of 2025, the Department of Construction must disburse 1,835,156 billion VND. Of which, the capital for site clearance accounts for about 30%.

English: The news

Comrade Hoang Van Dong, Provincial Party Committee member, Director of the Department of Construction delivered the opening speech at the conference.

In the plan to implement the peak campaign to complete the disbursement of public investment capital in 2025, the Department of Construction has assigned specific tasks and responsibilities to the departments under the Department, the Provincial Traffic Construction Investment Project Management Board, the Provincial Civil and Industrial Construction Investment Project Management Board, the Construction Investment Project Management Boards of the areas, the People's Committees of communes and wards where the project passes through in site clearance work, and construction contractors to speed up the progress of implementation and disbursement of public investment capital.

The Department of Construction sets monthly targets to mobilize the maximum participation of relevant departments, offices, units and contractors. By December 31, 2025, the entire remaining capital according to the plan will be disbursed, contributing to the completion of the target of disbursing public investment capital of the whole province.

English: The news

Construction unit leaders spoke and discussed and committed to project progress at the conference.

To achieve this goal, the Department of Construction has synchronously and drastically deployed tasks and solutions. In particular, assigning project management boards (units entrusted with project management) to increase the frequency of inspections, closely monitor the construction, and grasp the construction progress. Requiring contractors to focus resources, increase equipment and labor, and take advantage of favorable weather to organize construction in "3 groups, 4 shifts", throughout holidays and weekends.

At the same time, request project management boards to handle, or recommend strict handling of contractors who violate the progress and quality according to the contract. If necessary, report to competent authorities to terminate the contract and replace or add another contractor, especially for projects with a required completion time in 2025...

English: The news

The representative of the commune leader with the project passed by spoke at the conference.

At the conference, leaders of project management boards, People's Committees of communes and wards, and construction contractors focused on discussing and clarifying a number of difficulties and obstacles in implementing site clearance and project construction; proposing a number of solutions to speed up the site clearance plan and construction implementation to ensure progress and quality of the project.

English: The news

Leaders of communes where the project passes through sign commitments on site clearance progress to serve project implementation.

English: The news

Leaders of construction contractors signed a commitment to speed up construction progress of projects.

On that basis, leaders of project management boards, construction contractors and People's Committees of communes and wards where the project passes have signed commitments with the Department of Construction to carry out the assigned workload, speed up site clearance and construction progress, and ensure that by December 31, the peak campaign on disbursement of public investment capital in 2025 is completed.

Source: https://sxd.thanhhoa.gov.vn/thong-tin-hoat-dong-nganh/dam-bao-den-ngay-31-12-hoan-thanh-chien-dich-cao-diem-giai-ngan-von-dau-tu-cong-nam-2025-629334


Comment (0)

No data
No data

Same category

Vietnamese Films and the Journey to the Oscars
Young people go to the Northwest to check in during the most beautiful rice season of the year
In the season of 'hunting' for reed grass in Binh Lieu
In the middle of Can Gio mangrove forest

Same author

Heritage

Figure

Enterprise

Yen Nhi's national costume performance video has the highest views at Miss Grand International

News

Political System

Destination

Product