Hoa Binh Hydropower Plant Expansion Construction Site, July 2025
EVN's Hoa Binh Hydropower Extension Project consists of two units with a total capacity of 480 MW, and is one of the key projects in the electricity industry. The installation of the units at the site is considered a "difficult problem" when it is necessary to construct super-heavy structures in a time nearly half the usual time. Normally, installing a unit with such a large capacity takes about 7-8 months, but with urgent requirements, the construction units are determined to complete it in just over 4 months.
According to Mr. Bui Phuong Nam, Director of Power Project Management Board 1 (EVNPMB1), to ensure progress, the forces have synchronously deployed optimal solutions: Organizing 3 continuous shifts, mobilizing human resources from other projects, and closely coordinating between construction and installation units. Notably, in adverse weather conditions due to the impact of storm No. 3, the construction site has not stopped operating, demonstrating the spirit of "not losing to storms".
At the machine installation booth, contractor Lilama10 is focusing on completing important stages such as mechanical rotation, centering, and equipment alignment. The machine's rotor weighs 585 tons, has a diameter of more than 11.2 meters, but requires extremely small installation tolerances - the flatness does not exceed 0.02mm/m. This is a key technical factor to ensure the stability and longevity of the equipment during operation.
Accompanying EVN and Vietnamese contractors, foreign experts from GE Group - the equipment supplier - are also working day and night to ensure the overall progress of the project.
After more than 3 years of implementation, with close direction from the Government and efforts from construction forces, the Hoa Binh Hydropower Expansion Project is preparing to enter the no-load test phase. When completed, the project will not only effectively exploit flood water resources to generate electricity, reducing the load on the existing generator, but also add about 500 million kWh/year to the national grid, contributing to increasing peak capacity and improving the efficiency of the power system.
Anh Tho
Source: https://baochinhphu.vn/du-an-thuy-dien-hoa-binh-mo-rong-tang-toc-thi-cong-san-sang-phat-dien-vao-thang-8-102250730085426049.htm