The project to renovate and upgrade District Road 195 has a total length of 7.8 km, with a total investment of about 95 billion VND. This project is divided into 2 implementation phases. In September 2023, phase 1 of the project was completed and put into use. Currently, Thanh Mien district is continuing to implement phase 2 with a length of 4.3 km. Up to now, the construction unit is completing the items of large box culverts, embankments, cross-culverts, roadbed embankment, drainage system... The total workload has reached over 50%, ensuring the set plan. The construction unit strives to complete the gravel grading and asphalt concrete paving in May.
Previously, Thanh Mien district had promoted and mobilized 133 households in Le Hong, Doan Ket, and Hong Quang communes to donate land and clear constructions on the land to implement the project. Up to now, more than 80 households have agreed to hand over the land. The remaining households requested Thanh Mien district to arrange compensation funds and support for site clearance.