On July 14, the Standing Committee of Hai Phong City Party Committee listened to reports and gave opinions on investment policies: Investment project to build and operate infrastructure of Thuy Nguyen Industrial Park (phase 1) and Investment project to develop infrastructure of Tien Lang Airport Industrial Park - Area B.
Specifically, the Thuy Nguyen Industrial Park Infrastructure Investment and Construction Project (phase 1) is invested by Taseco Hai Phong Industrial Park Joint Stock Company. The project has a scale of 247.8 hectares, implemented in the wards of Bach Dang, Nam Trieu, Hoa Binh . The total investment capital of the project is 3,939.7 billion VND.
Project implementation progress from the third quarter of 2025 to the fourth quarter of 2026 will carry out site clearance work. It is expected that from the fourth quarter of 2028 onwards, the investment in infrastructure construction of the Industrial Park will be completed and put into operation and business.
Hai Phong agreed on the investment policy for the project to build and operate the infrastructure of Thuy Nguyen Industrial Park (phase 1) and Tien Lang Airport Industrial Park - Area B. |
Next is the project to invest in developing the infrastructure of Tien Lang Airport Industrial Park - Area B, invested by CEO Industrial Park Development Joint Stock Company. The project has a scale of 186.4 hectares, implemented in Chan Hung commune, in the South Hai Phong coastal economic zone. The total investment of the project is 2,795.3 billion VND.
Project implementation progress shall not exceed 36 months from the date the State decides to allocate land, lease land, or change land use purpose.
After listening to the reports and opinions of relevant units, Mr. Le Tien Chau, Secretary of the Hai Phong City Party Committee, unanimously approved the investment policy for the above two projects. The Secretary of the Hai Phong City Party Committee emphasized that during the implementation process, the projects closely followed and were consistent with the regional planning and Hai Phong city planning approved in Decision No. 1516/QD-TTg.
The Standing Committee of the City Party Committee assigned the City People's Committee to direct the Departments, branches, and investors in the process of attracting investment to implement the commitment to prioritize land funds for lease to high-tech enterprises, small and medium-sized enterprises, and innovative startups in accordance with the direction in Resolution 68-NQ/TW dated May 4, 2025 of the Politburo on private economic development.
For investors, it is necessary to arrange land area in the Industrial Park to develop accommodation as well as cultural and sports facilities to serve workers and laborers. Relevant departments, branches and units guide project investors to carry out procedures for establishing enterprises in the city.