Cho Mai - Tan My road project is committed to be completed in July 2025.

Contractors have resumed work.

The Mai - Tan My market road project was approved by the Provincial People's Committee (now Hue City People's Committee) in 2016, starting at the intersection with National Highway 49 at Km10+217 on Pham Van Dong Street, ending at the intersection with Phu My - Thuan An Street with a total length of more than 4km, the cross-section of the route is completed according to the plan with a 36m roadbed.

The objective of the project is to invest in the construction of the planned route, contributing to creating momentum to accelerate the implementation of the planning of Thuan An 2 ward, meeting the transportation needs of the area and creating a premise for attracting investors to build infrastructure.

The project has a total investment of nearly 195 billion VND; of which, the construction value is about 123 billion VND, site clearance is more than 33 billion VND, the investment capital is from the central budget with targeted support under the target program for socio -economic development of regions according to the decision of the Prime Minister. The entire project consists of 22 bid packages, of which the consulting bid packages have been basically completed. In particular, 3 construction bid packages, namely bid packages 11, 14 and 19, are still being implemented.

After many times of extending the contract progress, handling violations of contractors, the project stopped for a long time, until now, the People's Committee of Hue City has decided to approve the adjustment of the Mai - Tan My market road project, contractors have actively resumed construction on the site.

According to the reporter's records, by mid-July, the contractor had completed the asphalt paving of about half of the route in package 4 after completing the gravel grading. This is the package with the most "unfinished" road surface construction, but so far the progress has been guaranteed.

Urgently complete the remaining packages

According to the Hue City Urban Development and Investment Project Management Board, the construction progress of package No. 11, including the entire construction and installation part of the 2.2km section implemented by Dong Tam Construction Company Limited with a contract value of more than 58 billion VND, has been basically completed. Currently, only the asphalt concrete pavement remaining at the junction between the project and National Highway 49 (about 2m wide) and the median strip intersections in the middle of the route. The project has a connection point with National Highway 49 at the Km0 intersection of package No. 11. From July 1, 2025, the Project Management Board has submitted a dossier to the competent authority requesting approval of the connection intersection, and at the same time coordinated and closely followed up so that the connection point would soon be approved and licensed to asphalt the entire section and complete the project.

In package 14, including the entire construction and installation of the more than 2km section, the construction of the roadbed, cross-road box culverts, terrain drainage culverts, etc. has been basically completed. Some main items have not been completed, such as the embankment of the sidewalk and median strip, traffic safety items and some other auxiliary items. Package 14 is implementing asphalt concrete paving on the right side of the route and completing the construction of the 3rd layer of crushed stone aggregate on the left side of the route, proceeding to asphalt concrete paving the road surface and completing the project.

Similarly, package 19 includes the construction of additional items such as curbs, curb ditches, tree planting, longitudinal drainage system, and lighting system along the entire route. Up to now, the tree items have been completed, the longitudinal drainage system, drainage manholes within the scope of package 11, electrical system, and lighting system have been basically completed. For some unfinished items, the functional unit is urging contractors to speed up the progress to complete the package.

Responding to voters' petitions at the 9th Session of the 8th City People's Council, the Hue City Urban Development and Construction Investment Project Management Board affirmed that the Cho Mai - Tan My road project will be completed in July 2025.

Mr. Dang Quang Ngoc, Deputy Director of the Hue City Urban Development and Construction Investment Project Management Board, said that in order to carry out the remaining work according to the signed contract, the Project Management Board has worked with contractors of the remaining construction packages of the project on handling existing and arising problems and the construction plan in the coming time. Through the meeting, the contractors committed to completing the project this July.

(1) Merged from wards and communes of Phu Thuong, Phu An, Phu My; (2) Merged from wards and communes of Thuan An, Phu Hai, Phu Thuan

Article and photos: N. KHANH

Source: https://huengaynay.vn/kinh-te/xay-dung-giao-thong/hoan-thanh-cong-trinh-duong-cho-mai-tan-my-trong-thang-7-155898.html