Construction on the Dong Dang - Lang Son expressway is progressing rapidly day and night.

TPO - On the Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway project site, more than 3,000 officials, engineers, and workers are working diligently day and night, persistently staying at hundreds of construction sites to drill through mountains and open roads, with the goal of opening the entire route by December 19th.

Báo Tiền PhongBáo Tiền Phong15/12/2025

c1d1189fb29c3dc2648d.jpg
The Dong Dang - Tra Linh Expressway has a total length of 121 km, divided into two investment phases with a total investment of nearly 23,000 billion VND. Spanning across Lang Son and Cao Bang provinces, phase 1 of the project is over 93 km long, including 64 overpasses crossing the Ky Cung and Bang Giang rivers, along with numerous streams and provincial roads.
a6ca90823a81b5dfec90.jpg
Given the geological structure and rugged terrain, coupled with the prolonged natural disasters of rain and floods in the area, this is one of the most challenging highway projects currently underway in the country.
c18d05c3afc0209e79d1.jpg
Overcoming challenges such as severe natural disasters, rugged terrain, and complex geological conditions, more than 3,000 project officials, engineers, and workers persevered on hundreds of construction sites to drill through mountains and open roads. To date, the value of output has reached 6,219/6,828 billion VND, equivalent to more than 91% of the plan for opening the route in phase 1.
4ce68aa820abaff5f6ba.jpg
Phase 1 of the Dong Dang - Tra Linh expressway project includes two tunnels through mountains, named after two locations associated with the 1950 Border Campaign: That Khe and Dong Khe. The That Khe tunnel (Trang Dinh commune, Lang Son province) is approximately 200m long and is located in Trang Dinh commune, Lang Son province. Currently, workers are constructing the outer foundation of the tunnel shell and cleaning the tunnel tubes.
689765d8cfdb408519ca.jpg
At the Dong Khe tunnel area (nearly 500m long), construction teams are focusing on completing the retaining walls, drainage system, roof structure, plaza area, and the road connecting the two tunnel entrances.
c6b510fbbaf835a66ce9.jpg
At the Km58 area (Dong Khe commune, Cao Bang province), after only two days of deployment, the construction force has laid more than 1km of asphalt concrete. Currently, the asphalt paving line is still operating day and night to increase production to approximately 2,000 tons per day.
2805684ac2494d171458.jpg
Working on the Dong Dang - Tra Linh construction site, driver Tran Van Cong said that he and his colleagues do not hesitate to work through the night and holidays to speed up production.
3a914edfe4dc6b8232cd.jpg
During this "final push" phase, construction teams are urgently laying asphalt pavement throughout Cao Bang province.
a98e15c0bfc3309d69d2.jpg
Mr. Nguyen Duc Tuan, Deputy General Director of Dong Dang - Tra Linh Expressway Joint Stock Company, said: "In the past period, we have continued to closely coordinate with consulting and supervision units and contractors to increase personnel and take advantage of favorable weather conditions to complete the paving of 7 km of asphalt concrete road surface in Cao Bang province from now until December 19th."
1f16a0580a5b8505dc4a.jpg
The repeated storms and floods this year have significantly impacted construction activities, causing nearly 100 billion VND in losses for investors and contractors. The actual construction time this year, starting from the site handover date (March 30th), was only about 3 months.
5c5e1a11b0123f4c6603.jpg
Although the project was scheduled for completion in the fourth quarter of 2026 according to the contract, the investors have overcome difficulties, ensuring the road will be open this year and striving to shorten the completion time by at least 3 months compared to the contract.
d5990bd7a1d42e8a77c5.jpg
Upon completion, the Dong Dang - Tra Linh project will connect with the Huu Nghi - Chi Lang and Bac Giang - Lang Son expressways to form a vital international expressway axis, connecting the trade of goods from Vietnam to China and Europe, contributing to enhancing the competitiveness of the economy and creating new impetus for socio-economic development in the Northeast region.

Source: https://tienphong.vn/rot-rao-thi-cong-cao-toc-dong-dang-lang-son-suot-ngay-dem-post1804923.tpo


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Enjoy the exciting night tours of Ho Chi Minh City.
A close-up view of the workshop making the LED star for Notre Dame Cathedral.
The 8-meter-tall Christmas star illuminating Notre Dame Cathedral in Ho Chi Minh City is particularly striking.
Huynh Nhu makes history at the SEA Games: A record that will be very difficult to break.

Same author

Heritage

Figure

Enterprise

A journey to explore Long Chau Lighthouse

News

Political System

Destination

Product