Construction of Cay Bridge has reached 30% completion.

Việt NamViệt Nam21/04/2024

image(1).png
Casting of girders at the Cậy ​​Bridge construction project. Photo: THÀNH CHUNG

The unit mobilized approximately 50 workers and more than a dozen machines and equipment, divided into teams to construct the underwater sections and cast Super-T girders.

The Cay Bridge connects Cam Dong commune (Cam Giang district) and Hung Thang commune (Binh Giang district). The project is managed by the Provincial Investment and Construction Project Management Board.

The construction project is a Class II road in a flat area. The design speed is 80 km/h. The bridge is a permanent structure made of prestressed reinforced concrete, with a width of 30 m, divided into two separate bridge sections. The total length of the bridge is 182 m with 4 Super-T girder spans.

The construction contractor is the Hai Duong Irrigation – Licogi 18 – Bao Long Joint Venture. The construction supervision contractor is Thang Long Construction Quality Consulting and Supervision Joint Stock Company.

The project commenced on March 20, 2024, with a construction period of 390 days.

The investor requested the People's Committee of Binh Giang district to urgently complete the land clearance work and arrange resettlement for households that need to be relocated… in order to ensure the project's construction progress.

HN

Source

Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Same author

Di sản

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
Vietnam's longest red ceramic and flower-lined road - Spring of the Year of the Snake 2025

Vietnam's longest red ceramic and flower-lined road - Spring of the Year of the Snake 2025

Boat Dock

Boat Dock

Traditional boat racing in Da Nang City

Traditional boat racing in Da Nang City