Construction of Cay bridge faces difficulties due to high river water

Việt NamViệt Nam24/09/2024


3b4d51cb20078659df16.jpg
As of September 24, the Cay bridge project has reached 45% of the construction volume.

By September 24, the construction unit had completed 32 bored piles of 2 piers under the river, completed the construction of all left and right T2 piers, completed casting 48/48 super-T girders and all 12 M1 abutment piles. The construction rate is estimated at 45% of the volume, ensuring progress.

After storm No. 3 and its circulation caused heavy rain, the water level of the Sat River rose, affecting some construction items of the project. Although the construction unit has adjusted the construction schedule, focusing on construction items that can be deployed to ensure safety, the high and fast-flowing river water makes it difficult to transport materials. If this situation continues, it will affect the construction progress of the project.

76d45a01d1cc77922edd.jpg
Rising water level of Sat River affects construction of Cay Bridge

Currently, this project is stuck with the construction site of pier T3 and pier M2 on the Binh Giang district side, which involves nearly ten households in Hung Thang commune. The investor and contractor requested Binh Giang district to promptly hand over the site for construction, ensuring the progress of completing the bridge construction as planned in April 2025.

The Cay Bridge construction investment project belongs to the bypass of provincial road 394, Hai Duong province, connecting Cam Dong commune (Cam Giang) and Hung Thang commune (Binh Giang). The project is invested by the Provincial Construction Investment Project Management Board.

The scale of the construction project is a level II plain road; design speed is 80km/h. The bridge is permanently built with prestressed reinforced concrete, the bridge width is 30m, divided into 2 separate bridge units. The total length of the bridge is 182m with 4 Super-T girder spans. The project will be implemented from March 2024.

PV


Source: https://baohaiduong.vn/thi-cong-cau-cay-gap-kho-do-nuoc-song-cao-393964.html

Comment (0)

No data
No data

Same tag

Same category

Braised Pig's Feet with Fake Dog Meat - A Special Dish of Northern People
Peaceful mornings on the S-shaped strip of land
Fireworks explode, tourism accelerates, Da Nang scores in summer 2025
Experience night squid fishing and starfish watching in Phu Quoc pearl island

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product