Vietnam.vn - Nền tảng quảng bá Việt Nam

Provincial Road 341 to be opened before April 30

Báo Quảng NinhBáo Quảng Ninh27/04/2023


The project to renovate and upgrade provincial road 341 (National Highway 18C) from Mong Cai Border Gate Economic Zone to Bac Phong Sinh Border Gate Economic Zone, phase 2, started on January 10, 2022. To date, more than 95% of the work has been completed. The investor and the contractor consortium have overcome difficulties, accelerated the construction progress, ensuring the entire route is opened before April 30 and completed and put into use in the second quarter of this year, 6 months ahead of the project implementation time.

Provincial Road 341 has so far completed more than 95% of the work, ensuring the route is open before April 30.
Provincial Road 341 has so far completed more than 95% of the work, ensuring the route is open before April 30.

The Project to Improve and Upgrade Provincial Road 341 (National Highway 18C) from Mong Cai Border Gate Economic Zone to Bac Phong Sinh Border Gate Economic Zone, Phase 2, was approved by the People's Committee of Quang Ninh province in Decision No. 4726/QD-UBND dated November 15, 2018, approved for adjustment in Decision No. 2279/QD-UBND dated July 12, 2021 with a total planning area of 34.12 hectares. Total investment of VND 297 billion.

Leaders of Quang Ninh Economic Zone Management Board inspected the project construction progress on the afternoon of April 26.
Leaders of Quang Ninh Economic Zone Management Board inspected the project construction progress on the afternoon of April 26.

The project investor is the Quang Ninh Economic Zone Management Board. The project has a route length of 13.83km. The starting point of the route is at Po Hen Bridge (Km88+195), Hai Son Commune center; the end point of the route connects with the end point of phase 1 at Km103+314, National Highway 18C. The roadbed is 9 meters wide; the road surface is 6 meters. This is a level III traffic project; the design speed is 60km/h. Construction progress is 660 days from the commencement date.

Taking advantage of favorable weather, the construction unit urgently constructed the section bordering Bac Son commune with Hai Son, ensuring the completion of this asphalt section on April 27-28.
Taking advantage of favorable weather, the construction unit urgently constructed the section bordering Bac Son commune with Hai Son, ensuring the completion of this asphalt section on April 27-28.

As soon as the site was available, the joint venture of contractors, Thanh Duong Company Limited and Tri Duc Investment, Development and Construction Joint Stock Company, mobilized human resources and machinery to urgently dig and fill the roadbed and drainage culverts; ensuring safe construction measures and traffic safety.

Construction unit of asphalt pavement, section through Than Phun village, Bac Son commune (Mong Cai)
Construction unit of asphalt pavement, section through Than Phun village, Bac Son commune (Mong Cai)

This is a project to renovate and upgrade the traffic route connecting the two border economic zones of Mong Cai and Bac Phong Sinh. The completed route will facilitate the circulation of goods, creating momentum for socio-economic development of Mong Cai city, Hai Ha district in particular and Quang Ninh province in general; gradually completing the infrastructure of the border area to implement the policy of stabilizing and migrating people in the border area to combine socio-economic development with protecting national sovereignty and security. Phase 1 of the project was implemented, completed and put into operation and use by the Quang Ninh Economic Zone Management Board from 2020.

The construction unit completed the last meters of drainage ditches along the entire route.
The construction unit completed the last meters of drainage ditches along the entire route on April 26.

By mobilizing maximum forces and means to construct the project items. Up to now, the investor and the construction unit have completed the asphalt paving of the entire route, ensuring the completion of the project ahead of schedule. This is a project to celebrate the 60th anniversary of the founding of Quang Ninh province. The completed project put into use has concretized the Construction Planning of Quang Ninh province to 2030, with a vision to 2050 and beyond 2050.



Source

Comment (0)

No data
No data
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together
Hanoi is strange before storm Wipha makes landfall
Lost in the wild world at the bird garden in Ninh Binh
Pu Luong terraced fields in the pouring water season are breathtakingly beautiful
Asphalt carpets 'sprint' on North-South highway through Gia Lai

Heritage

Figure

Business

No videos available

News

Political System

Local

Product