Vietnam.vn - Nền tảng quảng bá Việt Nam

Ho Chi Minh City: Construction of Ben Thanh Metro Line 2 project underway

Báo Đầu tưBáo Đầu tư21/02/2024


Ho Chi Minh City: Construction of metro line 2 project Ben Thanh - Tham Luong begins

On February 17, at Ben Thanh Station, the Management Board of Urban Railways (MAUR) organized the construction of the Ben Thanh - Tham Luong metro line 2 project in the year of the Dragon 2024.

The project to build metro line 2 Ben Thanh - Tham Luong was approved by the City People's Committee in Decision No. 4474/QD-UBND dated October 11, 2010 and approved for adjustment in Decision No. 4880/QD-UBND dated November 14, 2019 with a total investment of VND 47,890.84 billion, using ODA loans from the Asian Development Bank (ADB), the German Reconstruction Bank (KfW), the European Investment Bank (EIB) and counterpart funds from the budget.

1
Mr. Bui Anh Huan, Deputy Head of MAUR shared: "In the atmosphere of the beginning of the new year, I am happy to announce that the technical infrastructure relocation work has met the conditions for simultaneous construction."

Mr. Bui Anh Huan, Deputy Head of MAUR, said that the project is more than 11 km long (of which the underground section is more than 9 km long; the elevated section is nearly 2 km long) with 10 stations (9 underground stations, 1 elevated station).

1
Metro Line 2 project passes through 6 districts.

The project passes through 6 districts: 1, 3, 10, 12, Tan Binh, Tan Phu with a total recovered area of 251,136 m2, total compensation and support costs are 3,753,610 billion VND . Up to now, the land handover rate has reached 86.69% (508/586 cases).

1
Mr. Nguyen Quoc Hien, Deputy Head of MAUR, gave lucky money to outstanding workers.

Previously, On June 22, 2023, MAUR held a groundbreaking ceremony for technical infrastructure works for the electricity category. Up to now, the relocation of technical infrastructure works has completed the selection of contractors for the relocation and reconstruction packages of water supply, drainage, lighting, signs, and traffic lights in December 2023.

1
Ms. Vu Minh Huyen, Deputy Head of MAUR, encouraged workers on the first day of the year.

MAUR announced that the project's technical infrastructure relocation has met the conditions for simultaneous construction and requested contractors to urgently mobilize workers and construction equipment.

1
Female workers on the construction site are ready to take on the task.

MAUR also requested the drainage contractor to coordinate with water and electricity contractors to carry out construction work immediately after the ceremony to ensure the progress agreed upon by all parties with the basic goal of completing the relocation of technical infrastructure works in 2024 to be ready for handover to the main contractor for tunnel and station construction in 2025.



Source

Tag: subway

Comment (0)

No data
No data
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?
Taste of the river region

Heritage

Figure

Business

No videos available

News

Political System

Local

Product