| Scene at the working session. |
After listening to the report, the Vice Chairman of the Provincial People's Committee acknowledged a number of contents that the locality had implemented according to previous instructions; however, the efficiency was not high, not achieving the desired results, as committed to the province.
Specifically, for the Yen Binh 2 Industrial Park Project, as of November 19, only 14/36 households within the 35-hectare area had been counted and counted for site clearance; the Dai Thang Social Housing Project (phase 2) has not yet had its planning approved; the Dong Tay Project has yet to resolve some issues.
![]() |
| Van Xuan ward leaders report at the meeting. |
Therefore, comrade Bui Van Luong requested Van Xuan ward to seriously learn from experience and speed up the progress of projects. Focus on clearing the land for Yen Binh 2 Industrial Park Project; by December 25, the planning of Dai Thang Social Housing Project (phase 2) must be approved...
![]() |
| Leaders of the Provincial Land Fund Development Center report. |
The Vice Chairman of the Provincial People's Committee also requested the leaders of Van Xuan ward to report daily progress to the provincial leaders. He emphasized that disbursement of public investment capital is a key task, directly affecting the progress of infrastructure construction and urban development. Relevant agencies need to continue to review difficulties and obstacles, and promptly resolve them to promote the progress of projects.