Ben Luc - Long Thanh Expressway strives to open two sections early

Báo Giao thôngBáo Giao thông05/09/2024


On September 5, providing information on the implementation status of the Ben Luc - Long Thanh expressway project, Mr. Dang Huu Vi, Director of the Southern Expressway Management Board (Vietnam Expressway Corporation) said that up to now, the total output of the project has reached about 85% of the plan.

Cao tốc Bến Lức - Long Thành nỗ lực thông xe sớm hai đoạn- Ảnh 1.

Overall, the Ben Luc - Long Thanh expressway packages have reached about 85%.

Of which, 5 packages (A2-1, A3, J2, A5, A7) have been basically completed. There are 8 packages (A1-1, A2.2-4, J1, A6-1, A6-2, A6-3, A6-4, A6-5) under construction.

According to Mr. Vi, from now until the end of 2024, we will try to open a section through Long An from the Ho Chi Minh City - Trung Luong Expressway to the intersection with National Highway 1 through Binh Chanh District. In the East, we will open a section from the intersection with National Highway 51 to the Phuoc An inter-port road.

Cao tốc Bến Lức - Long Thành nỗ lực thông xe sớm hai đoạn- Ảnh 2.

The road through the mangrove forest in Dong Nai has taken shape, forming a long silk strip across the green forest.

In addition, there is another very important bridge on the route, Binh Khanh Bridge (package J1), which has so far reached 82% of construction volume.

The Project Management Board is coordinating and urging contractors to speed up progress, trying to remove difficulties, and bring the entire project to the finish line as soon as possible.

Cao tốc Bến Lức - Long Thành nỗ lực thông xe sớm hai đoạn- Ảnh 3.

Binh Khanh Bridge progress has reached about 82%.

Phuoc Khanh Bridge (package J3) is being re-bid. Phuoc Khanh Bridge crosses Long Tau River connecting Can Gio District (HCMC) and Nhon Trach District (Dong Nai). Previously, this bridge was built by a joint venture of Sumitomo Mitsui (Japan) - Cienco 4 (Vietnam).

By 2022, the Vietnam Expressway Corporation and the contractor had terminated the contract when the total volume reached 80.70%. The remaining main volume of this package includes the main girder, bridge deck and cable-stayed system, asphalt concrete, lighting system, railings, median strip, and main bridge drainage system.

Cao tốc Bến Lức - Long Thành nỗ lực thông xe sớm hai đoạn- Ảnh 4.

The pillars of Binh Khanh bridge are stretching out in the middle of the river.

"Phuoc Khanh Bridge is the critical part of the project. Only after this bridge is completed can the entire route be opened. Therefore, we are currently inviting bids again and trying to restart this project soon," said Mr. Vi.

The Ben Luc - Long Thanh Expressway is a key project in the North - South Expressway system. This expressway passes through 3 provinces and cities: Long An, Ho Chi Minh City and Dong Nai with a total length of nearly 58km, and a total initial investment of 31,320 billion VND.

The starting point of the route is in Ben Luc district (Long An) connecting to Ho Chi Minh City - Trung Luong expressway. The end point connects to National Highway 51 in Long Thanh district (Dong Nai).

The project started in July 2014 and was expected to be completed and put into use in 2019. However, the implementation process encountered many difficulties, so the construction time was prolonged. The investor also committed to completing the entire project in September 2025.



Source: https://www.baogiaothong.vn/cao-toc-ben-luc-long-thanh-no-luc-thong-xe-som-hai-doan-192240905103336606.htm

Comment (0)

No data
No data
Hanoi is strange before storm Wipha makes landfall
Lost in the wild world at the bird garden in Ninh Binh
Pu Luong terraced fields in the pouring water season are breathtakingly beautiful
Asphalt carpets 'sprint' on North-South highway through Gia Lai
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night

Heritage

Figure

Business

No videos available

News

Political System

Local

Product