Vietnam.vn - Nền tảng quảng bá Việt Nam

Da Nang removes obstacles, promotes disbursement of public investment capital

(Chinhphu.vn) – Da Nang City proactively decentralizes, strengthens coordination and resolutely implements solutions to promote the disbursement progress of public investment capital in 2025.

Báo Chính PhủBáo Chính Phủ24/09/2025

Đà Nẵng tháo gỡ vướng mắc, thúc đẩy giải ngân vốn đầu tư công- Ảnh 1.

Da Nang focuses on promoting disbursement of public investment capital in the last months of the year - Photo: VGP/LH

According to the report of the Department of Finance of Da Nang City, in 2025, the City was assigned more than 16,402 billion VND of public investment capital. As of August 31, the total disbursement value reached more than 6,805 billion VND, equal to 41.5% of the plan, higher than the same period in 2024 and the national average. It is estimated that by the end of September, the disbursed capital will reach about 8,200 billion VND, equivalent to 50% of the yearly plan.

Identifying the disbursement of public investment capital as an important task, from the beginning of the year, Da Nang City has proactively established and allocated detailed capital plans. The city requires units to commit to disbursement progress, and at the same time link implementation results with emulation and reward work.

Da Nang has established 9 working groups headed by the City People's Committee to resolve problems with backlogged and long-term projects, while urging the implementation of key and dynamic projects. Some units have achieved high disbursement rates such as the Management Board of Regional Construction Investment Projects under the City People's Committee (over 54%) and the Quang Nam Provincial Traffic Management Board (over 50%).

Despite positive changes, the disbursement progress has not yet met requirements due to difficulties in compensation, site clearance and fluctuations in construction material prices. Many projects are slow to be implemented due to difficulties in documents, procedures, as well as the arrangement of dumping sites and exploitation of landfills.

The City has identified the disbursement of public investment capital as a key political task that needs to be implemented regularly and continuously. From now until the end of the year, the City People's Committee will continue to direct resolutely, striving to complete the target of disbursing 100% of the public investment capital plan in 2025.

Recently, at a meeting to remove difficulties and obstacles to promote the disbursement of public investment capital in 2025, Chairman of the People's Committee of Da Nang City Pham Duc An frankly pointed out the existing problems, especially the delay in site clearance and difficulties in the supply of construction materials.

The Chairman of the City People's Committee requested that in the coming time, it is necessary to promote decentralization and authorization so that departments, branches and localities have enough authority to handle practical issues. At the same time, develop a manual for the grassroots level to reduce procedures and support effective project implementation. Regarding compensation and resettlement, it is required to ensure adequate essential infrastructure and comply with legal regulations.

Along with strengthening coordination between departments and branches, the Chairman of the People's Committee of Da Nang City encouraged localities and units to proactively propose projects, speed up the disbursement of public investment capital in 2025 and prepare well for the 2026 plan. "The general spirit is high determination, specific actions, close coordination and focus on practical solutions to ensure effectiveness," emphasized Chairman of the People's Committee of Da Nang City Pham Duc An.

Liu Xiang


Source: https://baochinhphu.vn/da-nang-thao-go-vuong-mac-thuc-day-giai-ngan-von-dau-tu-cong-102250924151647413.htm


Comment (0)

No data
No data

Same category

Western tourists enjoy buying Mid-Autumn Festival toys on Hang Ma Street to give to their children and grandchildren.
Hang Ma Street is brilliant with Mid-Autumn colors, young people are excitedly checking in non-stop
Historical message: Vinh Nghiem Pagoda woodblocks - documentary heritage of humanity
Admiring Gia Lai coastal wind power fields hidden in the clouds

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;