- As of June 17, the progress of site clearance for the Dong Dang (Lang Son) - Tra Linh ( Cao Bang ) expressway project through Van Lang and Trang Dinh districts has reached 98%.
However, according to statistics, there are currently 48 households in 2 districts that have not yet handed over residential land and agricultural land with an area of 6.85 hectares; and 7 households have not yet moved their houses out of the project implementation area with a length of about 1 km.
Specifically, in Van Lang district, there are 24 households that have not yet handed over residential land and agricultural land, and 4 households that have not yet moved their houses out of the project implementation area; in Trang Dinh district, there are 24 households that have not yet handed over residential land and agricultural land, and 3 households that have not yet moved their houses.
Cases where the land has not been handed over due to: households requesting to be granted red books in the resettlement area before handing over the land; not agreeing to the compensation plan and requesting to re-verify the origin of the land...
It is known that the People's Committees of Trang Dinh and Van Lang districts are continuing to propagate and mobilize households that have not yet handed over and completed legal documents for compensation in order to carry out the enforcement process according to regulations.