Hanoi: Finished fixing the phenomenon of mud rising to the ground in the Nui Truc alley area

On the afternoon of August 6, information from the Hanoi Urban Railway Management Board (MRB) said that the phenomenon of mud overflowing to the ground during the tunnel drilling process has been controlled, the affected area is currently being cleaned, the scope of the area is narrowed and the ground is restored.

Báo Công an Nhân dânBáo Công an Nhân dân06/08/2025

Previously, in the early morning of August 6, 2025, in the Nui Truc alley area, during the tunnel construction process using TBM No. 2 (Tunnel Boring Machine) of the underground section of the Hanoi Pilot Urban Railway Project, the Nhon - Hanoi Railway Station section, a mixture of mud and water overflowed to the ground.

Immediately after discovering the incident, the investor, consultants, contractors and local authorities were present at the scene to coordinate and supervise the handling work. The project urgently mobilized 30 personnel and 5 mud suction trucks, specialized equipment, sandbags and materials, and temporarily fenced off the area to conduct zoning, collection, treatment of mud, cleaning the area of the mud mixture that erupted, while closely monitoring all TBM construction activities, ...

The phenomenon of mud rising to the ground surface during the tunnel drilling process of the urban railway project has been resolved -0
Mud overflowing onto the road surface.

After a few hours of handling, the mudflow has been controlled, the affected area is currently being cleaned, the scope is narrowed and the site is being restored. According to initial assessment, the affected area is small and is under control, no damage to people or surrounding works or infrastructure has been recorded.

The phenomenon of mud rising to the ground surface during the tunnel drilling process of the urban railway project has been resolved -0
Sludge suction trucks were mobilized to handle the incident.

It is known that ground monitoring has been continuously deployed throughout the tunnel drilling process and is still within the allowable limit index, ensuring safety. The second TBM of the Project has drilled 1040m of tunnel, currently continuing construction under the close supervision of consultants and investors.

Source: https://cand.com.vn/doi-song/ha-noi-khac-phuc-xong-hien-tuong-bun-trao-len-mat-dat-khu-vuc-ngo-nui-truc-i777207/


Comment (0)

No data
No data
Wild beauty on Ha Lang grass hill - Cao Bang
Vietnam Air Force practices preparing for A80
Missiles and combat vehicles 'Made in Vietnam' show off their power at A80 joint training session
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2

Heritage

Figure

Business

No videos available

News

Political System

Destination

Product