After more than 3 years of being approved by the Prime Minister for investment policy, the Tam Anh - An An Hoa Industrial Park project has only cleared 10ha/435ha of land.
For more than 3 years, Tam Anh - An An Hoa Industrial Park has only cleared 10 hectares of land.
After more than 3 years of being approved by the Prime Minister for investment policy, the Tam Anh - An An Hoa Industrial Park project has only cleared 10ha/435ha of land.
Vice Chairman of Quang Nam province, Mr. Ho Quang Buu, has just issued a document requesting to speed up the progress of compensation and site clearance for the Tam Anh - An An Hoa Industrial Park Infrastructure Investment and Construction Project.
Accordingly, Quang Nam province requested Nui Thanh district, the Department of Natural Resources and Environment, and the Management Board of Economic Zones and Industrial Parks of the province to coordinate to promptly resolve documents, procedures, and existing issues and problems in the compensation and site clearance work of the project.
In case of problems beyond authority, promptly report to the Provincial People's Committee for consideration and resolution...
According to the proposal of An An Hoa Industrial Park and Urban Area Joint Stock Company, the investor implementing the Tam Anh - An An Hoa Industrial Park project, the project's site clearance is currently facing many difficulties.
According to this enterprise, it has been 3 years and 6 months since the Prime Minister approved the project's investment policy, but compensation work has only been completed on 10.66 hectares/435.6 hectares.
An An Hoa Industrial Park and Urban Area Joint Stock Company requested Quang Nam province to pay attention to site clearance for the project, to start construction soon and attract secondary investors.
Tam Anh - An An Hoa Industrial Park project has adjusted its implementation progress into 4 phases.
Specifically, phase 1 will invest in an area of about 111 hectares; phase 2 will invest in an area of about 137 hectares; phase 3 will have an area of about 147 hectares; phase 4 will invest in the remaining area of the project of 40.8 hectares... The project is expected to be completed in 2028.
In March 2021, the Prime Minister decided to invest in the construction and business of infrastructure of Tam Anh - An An Hoa industrial park (Nui Thanh district).
The project is implemented by An An Hoa Industrial Park and Urban Joint Stock Company with a land use scale of 435.8 hectares. The total estimated investment capital is 1,540 billion VND; of which the investor's capital contribution is 462 billion VND.