These days, all key construction works and projects in Ha Tinh are bustling with construction spirit. Under the favorable early season sunshine, the working atmosphere is extremely urgent. Groups of workers are putting all their efforts into "racing" against time, speeding up the construction progress to soon bring the project to the finish line on schedule, creating momentum for the socio-economic development of the locality.

The project to upgrade and expand the inter-commune road of Thach Ngoc and Ngoc Son (Thach Ha) is currently at over 70% progress.
The project to upgrade and expand the inter-commune road of Thach Ngoc and Ngoc Son (Thach Ha) started in December 2024 with a total capital of 30 billion VND, and is expected to be completed by the end of December 2025. When completed, this route will connect the two communes of Thach Ngoc and Ngoc Son, significantly improving travel and freight conditions, contributing to promoting economic development in the region. Up to this point, contractors have completed the roadbed, installed drainage ditches, culverts across the road, etc. with the total volume of the route reaching over 70%.
Mr. Le Ngoc Tai - technical officer of Nguyen Ha Investment and Construction Joint Stock Company said: "To ensure progress and quality, the unit is currently arranging 2 parallel construction teams on the route. This allows the unit to speed up the leveling and filling progress at both ends at the same time, making the most of the sunny weather so that the ground is compacted to the highest requirements. With the efforts of technical staff and workers, we are focusing on completing the items, bringing the project to the finish line on schedule soon".
In addition to the above project, in 2025, the Thach Ha District Construction Investment Project Management Board is implementing 30 works and projects with a total investment of more than 2,500 billion VND. In the first months of the year, due to complicated weather developments and heavy rain, the construction process was interrupted, somewhat affecting the progress of the projects. Therefore, at this time, the board is actively urging contractors to mobilize all resources to ensure the progress of the projects as soon as possible.

Urgent construction atmosphere at the project to renovate and upgrade the sidewalk and technical infrastructure system of Nguyen Du street (from Tran Phu street to Nguyen Cong Tru street).
Along with regional traffic connection projects, urban infrastructure renovation and upgrading are also being focused on by investors and contractors. At the project to renovate and upgrade the sidewalk and technical infrastructure system of Nguyen Du Street (from Tran Phu Street to Nguyen Cong Tru Street), groups of workers from Tan Hai Son Construction Joint Stock Company are working diligently.
The project will be implemented from July 2023, with a total investment of more than 90 billion VND, and is expected to be completed by the end of September 2025. This project is not simply about re-paving the sidewalk, but also includes undergrounding the technical system, improving drainage, upgrading lighting, etc., to create a civilized and modern street, contributing significantly to changing the face of Ha Tinh City.


Mr. Vo Xuan Hai - technical officer of Tan Hai Son Construction Joint Stock Company shared: "Determining this is a key project of the city, directly affecting people's lives and urban beauty, the company always strives to overcome all difficulties. We have mobilized maximum labor, techniques and machinery to divide into 5 independent but well-coordinated construction teams, making the most of favorable weather conditions to speed up progress on many items at the same time, with the ultimate goal of bringing the project to the finish line soon".
According to Mr. Hai, thanks to the reasonable arrangement of human resources and machinery and taking full advantage of the weather, the project volume has now reached over 65%. In the coming time, the contractor will continue to closely monitor the construction site, encouraging workers to overcome difficulties to maintain this momentum.

One of the key projects that is "accelerating" strongly at this time is the construction and installation package to renovate and upgrade National Highway 8C from Thien Cam to National Highway 1 (part of the project to renovate and upgrade National Highway 8C) invested by the Ha Tinh Department of Construction (formerly the Ha Tinh Department of Transport).
This is a project of special significance, directly connecting Thien Cam tourist area with National Highway 1, creating a smooth and convenient traffic axis for tourists and commercial activities, contributing to the economic development of the region. The package has a total investment of 221 billion VND, started in October 2023, and is expected to be completed in October 2025.
At the construction site from Km0+00 to Km4+800, Bien Dong Construction and Consulting Joint Stock Company is closely following the progress, making the most of favorable weather to lay the first meters of asphalt. The unit has mobilized 20 locomotives of various types and nearly 50 skilled workers to work continuously.


Mr. Nguyen Viet Ngoc - Commander of Bien Dong Consulting and Construction Joint Stock Company shared: "The sunny weather helps us effectively carry out stages that require dry ground such as foundation, crushed stone grading and especially asphalt paving. Asphalt paving in favorable conditions not only ensures the quality of the project but also creates excitement for the workers, speeding up the overall progress. Thanks to the efforts of working day and night, we have completed nearly 50% of the volume, closely following the contract schedule."
According to information from the Ha Tinh Department of Construction, the entire upgraded route of National Highway 8C from Thien Cam to National Highway 1 is 11 km long with the participation of 9 contractors. "To bring the package to the finish line soon, we are closely following the construction site, regularly checking and urging, and promptly removing difficulties and obstacles that arise. The fact that contractors are proactively "welcoming the sun", working overtime, and increasing shifts is a very positive signal. Thanks to proactively implementing solutions, the package has so far achieved more than 42% of the volume, ensuring the set progress" - Mr. Ho Thanh Binh, Project Management Director emphasized.

At this time, the Provincial Traffic Construction Investment Project Management Board is also closely following the construction site, urging contractors to make efforts to speed up the progress of the projects. It is known that in 2025, the board is implementing 3 key traffic projects with a total investment of more than 2,400 billion VND.
Mr. Le Viet Hoa - Deputy Director of the Provincial Traffic Construction Investment Project Management Board said: "To ensure the progress and quality of these large-scale projects, we focus on drastic management and operation. The Board regularly organizes field meetings, closely monitors and urges contractors to mobilize maximum resources for implementation. We also develop flexible construction organization solutions, closely matching the progress of site handover, in order to speed up the overall progress. The unit sets up progress critical lines and scientific technical targets, both to minimize the adverse effects of the weather and strictly adhere to the construction sequence, ensuring technical and quality of the project as a top priority."
With the strong participation of the investor, the great efforts of the contractors and favorable weather conditions, the construction atmosphere at key construction sites in Ha Tinh is taking place very urgently. The close and flexible coordination in management and construction organization, along with the enthusiastic working spirit of the team of engineers and workers have been creating positive movements, promising that the works and projects will reach the finish line on time or earlier than planned, contributing significantly to infrastructure development and promoting the local socio-economic development in the coming time.
Source: https://baohatinh.vn/khong-khi-khan-truong-tren-cac-cong-truong-lon-o-ha-tinh-post287445.html